57 E MARKET ST 90291

Certificate Information: 57 E MARKET ST 90291

Application / Permit
22016-10000-19488
Plan Check / Job No.
B22LA12668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
eplan Tenant improvement to (e) studio/apartment for new non-load bearing partitions, finishes, skylights, and alterations to roof framing.
Permit Issued
Issued on 9/27/2022
Issuing Office
Current Status
Permit Finaled on 4/24/2023

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 MICHAEL LOPEZ
Corrections Issued 7/22/2022 MICHAEL LOPEZ
Quality Review Completed 7/29/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/25/2022 MICHAEL LOPEZ
Plan Check Approved 9/6/2022 MICHAEL LOPEZ
Issued 9/27/2022 APPLICANT
Permit Finaled 4/20/2023 FARHAD DADBIN

Permit Application Clearance Information

DAS Clearance Cleared 8/22/2022 Samuel Gonzalez

Contact Information

Architect Leong,, Wayne George; Lic. No.: C24216 PO BOX 2      ST HELENA, CA 94574
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1212 ABBOT KINNEY BLVD #A      LOS ANGELES, CA 90291
Engineer John,, Benjamin M; Lic. No.: S6932 1541 SE MAPLE AVE      PORTLAND, OR 97214

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 10/14/2022 Partial Inspection GRANT WOODS
Light Gage Steel Frame 12/1/2022 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 12/8/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 12/8/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 12/19/2022 Approved SORIN CIRSTOIU
Drywall Nailing 12/19/2022 Corrections Issued FARHAD DADBIN
Interior/Exterior Lathing 1/13/2023 Partial Approval FARHAD DADBIN
Wood Frame 1/18/2023 Not Ready for Inspection FARHAD DADBIN
Special/Order Compliance 1/23/2023 Not Ready for Inspection FARHAD DADBIN
Special/Order Compliance 1/27/2023 Conditional Approval FARHAD DADBIN
Deputy Drilled-In Anchors 2/7/2023 Approved FARHAD DADBIN
Final 3/24/2023 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Not Ready FARHAD DADBIN
Final 4/20/2023 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/20/2023 Approved FARHAD DADBIN