1717 1/2 W SCOTT AVE 90026

Certificate Information: 1717 1/2 W SCOTT AVE 90026

Application / Permit
22016-10000-19327
Plan Check / Job No.
B22LA12560
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert 21'-4"x19' (405 SF) Garage into new 1 bedroom ADU and add 64 sq ft Bathroom.
Permit Issued
Issued on 1/12/2023
Issuing Office
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/8/2022 JOE VO
Corrections Issued 7/8/2022 JOE VO
Applicant returned to address corrections 7/10/2022 JOE VO
Plan Check Approved 9/29/2022 JOE VO
Issued 1/12/2023 APPLICANT
CofO in Progress 7/14/2023 THOMAS LOGRASSO
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/9/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 9/9/2022 WALLIE JONG
Grading Pre-Inspection Cleared 9/26/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 9/28/2022 WALLIE JONG
Sewer availability Cleared 9/28/2022 WALLIE JONG

Contact Information

Contractor J O Construction; Lic. No.: 1057456-B       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/7/2023 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 2/7/2023 Corrections Issued THOMAS LOGRASSO
Deputy Drilled-In Anchors 2/8/2023 Conditional Approval THOMAS LOGRASSO
PLUMBING-Rough 2/10/2023 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/14/2023 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 2/16/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 3/9/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Corrections Issued JOSE AVILA
Green Building Rough 3/9/2023 Not Ready for Inspection JOSE AVILA
HVAC-Rough 3/9/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/9/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/14/2023 Approved FREDDIE RIVERA
Green Building Rough 3/14/2023 Approved FREDDIE RIVERA
Pre-Inspection 3/14/2023 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 3/14/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/29/2023 Corrections Issued THOMAS LOGRASSO
Insulation 3/29/2023 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 3/29/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 4/3/2023 Approved THOMAS LOGRASSO
Drywall Nailing 4/3/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/3/2023 Approved THOMAS LOGRASSO
Shower Pan 4/3/2023 Approved THOMAS LOGRASSO
Sewer 5/2/2023 Not Ready for Inspection THOMAS LOGRASSO
Sewer 5/8/2023 Approved THOMAS LOGRASSO
Final 6/30/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 6/30/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Required THOMAS LOGRASSO
Smoke Detectors 6/30/2023 Approved THOMAS LOGRASSO
Final 7/6/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 7/11/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 7/11/2023 Approved THOMAS LOGRASSO