956 1/2 N GLEN ARBOR AVE 90041
Certificate Information: 956 1/2 N GLEN ARBOR AVE 90041
- Application / Permit
- 22016-10000-19299
- Plan Check / Job No.
- B22LA12544
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert existing 437 SF crawl space below duplex into an ADU per CA Govt. Code 65852.2(e)(1)(C).
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | JAD BASMA |
| Corrections Issued | 7/17/2022 | JAD BASMA |
| Quality Review Completed | 7/28/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 9/14/2022 | JAD BASMA |
| No Progress | 6/22/2023 | JAD BASMA |
| Plan Check Approved | 7/25/2023 | JAD BASMA |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 5/29/2024 | ALIZAH MAYAGOITIA |
| No Progress | 5/30/2024 | CHARLES BOGHOSKHAN |
| CofO in Progress | 5/30/2024 | CHARLES BOGHOSKHAN |
| No Progress | 6/4/2024 | CHARLES BOGHOSKHAN |
| CofO in Progress | 6/4/2024 | CHARLES BOGHOSKHAN |
| Permit Finaled | 7/3/2024 | DEROLD HAUFF |
| CofO Issued | 7/3/2024 | DEROLD HAUFF |
| Permit Finaled | 7/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/27/2022 | CINDY QI |
| Sewer availability | Cleared | 7/27/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 12/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 1/22/2024 | Corrections Issued | ROY SPAULDING |
| Wood Frame | 1/22/2024 | Partial Approval | ROY SPAULDING |
| Insulation | 2/6/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/8/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | CRAIG VAUGHAN |
| Final | 5/15/2024 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/15/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Final | 5/21/2024 | Conditional Approval | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 5/28/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |