153 S LARCHMONT BLVD 90004
Certificate Information: 153 S LARCHMONT BLVD 90004
- Application / Permit
- 22016-10000-19277
- Plan Check / Job No.
- B22LA12522
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/Exterior remodel to (E) one-story Single Family Dwelling. Scope of work to include Kitchen remodel and bathroom remodels. Exterior scope of work limited to revisions to rear walls to accommodate doors and extension of (E) deck at rear.
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/20/2023
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 6/28/2022 | CHRISTOPHER KOMANCHECK |
| Issued | 8/10/2022 | APPLICANT |
| Permit Finaled | 4/19/2023 | STUART CHAPMAN |
Permit Application Clearance Information
| HPOZ | Cleared | 8/1/2022 | LYDIA CHAPMAN |
Contact Information
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/8/2022 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/8/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 11/8/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/8/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 11/14/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 11/14/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/18/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/28/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 2/24/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 2/24/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/24/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/24/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/24/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/29/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/19/2023 | Approved | STUART CHAPMAN |
| Final | 4/19/2023 | Permit Finaled | STUART CHAPMAN |
| PLUMBING-Final | 4/19/2023 | Approved | STUART CHAPMAN |