8723 W ALDEN DR 90048
Certificate Information: 8723 W ALDEN DR 90048
- Application / Permit
- 22016-10000-19096
- Plan Check / Job No.
- B22LA12329
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- ePLan The project scope involves a tenant improvement of existing workroom #107 for the installation of a CT scanning imaging machine for small specimen analysis. Scope includes the removal of existing workstations, saw cutting of the slab on grade for placement of a thickened pad for installation of the new CT machine, installation of new work stations, interior finish upgrades and supporting MEP work.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/13/2024
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/4/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/22/2022 | FARSHAD ALIMOHAMADI |
| Issued | 8/8/2023 | APPLICANT |
| Permit Finaled | 11/13/2024 | MARTIN TAVITIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Henrich,, Steven A; Lic. No.: C27292 | 863 N. LA FAYETTE PARK PLACE LOS ANGELES, CA 90026 |
| Contractor | Lcs Constructors Inc; Lic. No.: 640058-B | , |
| Contractor | Lcs Constructors, Inc.; Lic. No.: 640058-B | , |
| Engineer | Franco,, Richard; Lic. No.: NA4886 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 8/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 8/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 8/22/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 8/22/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 8/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 8/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 8/24/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 8/24/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 9/1/2023 | Conditional Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 9/5/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 9/8/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 9/25/2023 | Approved | ALFREDO LOPEZ |
| Light Gage Steel Frame | 9/25/2023 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 9/28/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 9/28/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 9/19/2024 | Conditional Approval | MARTIN TAVITIAN |
| Green Building Final | 9/19/2024 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 9/19/2024 | Approved | MARTIN TAVITIAN |
| Final | 10/15/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 11/13/2024 | Permit Finaled | MARTIN TAVITIAN |