9902 S VAN NESS AVE 90047

Certificate Information: 9902 S VAN NESS AVE 90047

Application / Permit
22016-10000-19004
Plan Check / Job No.
B22LA12276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) 2-CAR GARAGE (1-CAR TO REMAIN 208.3 SF) & RECREATION ROOM TO BE CONVERTED TO ADU (572 SF) PER CA Govt code 65852.2(e)(1)(A).
Permit Issued
Issued on 7/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 JOSEPH RAFOLS
Corrections Issued 6/25/2022 JOSEPH RAFOLS
Building Plans Picked Up 6/29/2022 APPLICANT
Plan Check Approved 7/21/2022 ADAM HEGAZI
Issued 7/29/2022 APPLICANT
CofO in Progress 8/25/2023 ENRIQUE MIRELES
CofO in Progress 8/25/2023 ENRIQUE MIRELES
Permit Finaled 9/13/2023 DEROLD HAUFF
CofO Issued 9/13/2023 DEROLD HAUFF
Permit Finaled 9/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/6/2022 AMAAN MALIK
Sewer availability Cleared 7/6/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 7/15/2022 AMAAN MALIK

Contact Information

Contractor C G S Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/13/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/13/2022 Approved ENRIQUE MIRELES
Underground Mechanical 10/25/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/30/2023 Approved ENRIQUE MIRELES
METHANE-Rough 1/30/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/30/2023 Approved ENRIQUE MIRELES
Insulation 2/17/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Drywall Nailing 3/23/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/20/2023 Approved ENRIQUE MIRELES
Final 8/22/2023 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/22/2023 Approved ENRIQUE MIRELES
Smoke Detectors 8/22/2023 Approved ENRIQUE MIRELES