8577 W VENICE BLVD 90034
Certificate Information: 8577 W VENICE BLVD 90034
- Application / Permit
- 22016-10000-18997
- Plan Check / Job No.
- B22LA12265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- CONVERT (E) PRINT SHOP INTO CHILD DAY CARE CENTER.
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/27/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Applicant returned to address corrections | 7/7/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 9/1/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/20/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/24/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/22/2024 | MINA HABILI |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | FARHAD DADBIN |
| Permit Finaled | 2/10/2025 | DAVID TSAU |
| CofO Issued | 2/10/2025 | DAVID TSAU |
| Permit Finaled | 2/10/2025 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 8/16/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 8/23/2022 | KYLE WINSTON |
| Fire Marshal Fire Life Safety | Cleared | 10/18/2023 | RONILO MULAWIN |
| Encroachment in public way | Cleared | 2/22/2024 | KATHERINE MENDOZA |
Contact Information
| Contractor | Saldivar Construction Inc; Lic. No.: 1009987-B | 937 EAST 24TH STREET LOS ANGELES, CA 90011 |
| Engineer | Finley,, Lawrence Rufus; Lic. No.: C46606 | 1178 E 9TH ST LONG BEACH, CA 90813 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Masonry Frame | 3/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 3/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 4/1/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 2/5/2025 | OK to Issue CofO | FARHAD DADBIN |
| Reinforced Masonry Frame | 2/5/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/5/2025 | Approved | FARHAD DADBIN |