2113 S KERWOOD AVE 90025

Certificate Information: 2113 S KERWOOD AVE 90025

Application / Permit
22016-10000-18897
Plan Check / Job No.
B22LA12196
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing 850 sqft detached garage with laundry & work room into accessory dwelling unit (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A)) "COMPLY WITH DEPARTMENT ORDER effective date 06/14/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 847662.
Permit Issued
Issued on 11/7/2022
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 AUNG SOE
Corrections Issued 7/2/2022 AUNG SOE
Applicant returned to address corrections 9/1/2022 DANIEL SANJUAN
Plan Check Approved 9/28/2022 JOSEPH RAFOLS
Issued 11/7/2022 APPLICANT
CofO in Progress 8/30/2023 PETER RUBIO
Permit Finaled 6/14/2024 DANIEL SANCHEZ
CofO Issued 6/14/2024 DANIEL SANCHEZ
Permit Finaled 6/14/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Specific Plan Cleared 7/26/2022 ROBERT SANCHEZ
Address approval Cleared 7/28/2022 DINAH GARIN
Sewer availability Cleared 7/28/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/8/2022 DINAH GARIN
Construction near power lines Cleared 9/15/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/28/2022 JOSEPH RAFOLS

Contact Information

Contractor Howard Construction Llc; Lic. No.: 1080061-B       ,
Engineer Wu,, Shu; Lic. No.: C90391 136 LOST HILLS      IRVINE, CA 92618

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/22/2022 Corrections Issued HAGOP BADOSSIAN
PLUMBING-Rough 12/22/2022 Corrections Issued HAGOP BADOSSIAN
BUILDING-Rough-Frame 1/4/2023 Corrections Issued JOHN TCHANG
Footing/Foundation/Slab 1/4/2023 Approved JOHN TCHANG
PLUMBING-Rough 1/4/2023 Approved JOHN TCHANG
BUILDING-Rough-Frame 1/11/2023 Corrections Issued JOHN TCHANG
PLUMBING-Rough 1/11/2023 Corrections Issued JOHN TCHANG
ELECTRICAL-Rough 1/19/2023 Partial Approval JOHN TCHANG
ELECTRICAL-Rough 2/7/2023 Partial Approval ROBERT CHAVEZ
Deputy Drilled-In Anchors 2/15/2023 Approved JOHN TCHANG
BUILDING-Rough-Frame 2/16/2023 Not Ready for Inspection ROBERT CHAVEZ
METHANE-Rough 2/16/2023 Approved ROBERT CHAVEZ
HVAC-Rough 4/3/2023 Corrections Issued PETER RUBIO
HVAC-Rough 4/7/2023 Approved PETER RUBIO
BUILDING-Rough-Frame 4/13/2023 Approved PETER RUBIO
Insulation 4/13/2023 Approved PETER RUBIO
Drywall Nailing 4/18/2023 Approved PETER RUBIO
Shower Pan 4/18/2023 Approved PETER RUBIO
Drywall Nailing 4/27/2023 Approved ROBERT CHAVEZ
Interior/Exterior Lathing 5/4/2023 Approved PETER RUBIO
Final 7/18/2023 Not Ready for Inspection PETER RUBIO
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Not Ready PETER RUBIO
Smoke Detectors 7/18/2023 Approved PETER RUBIO
Final 7/24/2023 Not Ready for Inspection RUBEN PEREZ
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Not Ready RUBEN PEREZ
Final 8/14/2023 Corrections Issued PETER RUBIO
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready PETER RUBIO
Final 8/17/2023 Not Ready for Inspection PETER RUBIO
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Not Ready PETER RUBIO
Final 8/29/2023 Conditional Approval PETER RUBIO
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved PETER RUBIO