1538 1/2 S DURANGO AVE 90035
Certificate Information: 1538 1/2 S DURANGO AVE 90035
- Application / Permit
- 22016-10000-18896
- Plan Check / Job No.
- B22LA12195
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting the existing detached garage to ADU PER STATE LAW
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | RACHEL BEYENE |
| Corrections Issued | 7/2/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/30/2022 | KHUONG TRUONG |
| Plan Check Approved | 12/14/2023 | KHUONG TRUONG |
| Issued | 12/18/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | ARAM AVEDISIAN |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
| CofO Issued | 12/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | CINDY QI |
| Sewer availability | Cleared | 8/9/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | CINDY QI |
Contact Information
| Contractor | Elm Construction; Lic. No.: 1099704-B | , |
| Contractor | Elm Group La Inc; Lic. No.: 1099704-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/23/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/2/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/23/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/24/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 6/24/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 7/5/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 7/9/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 7/9/2024 | Approved | SEAN HAUPT |
| METHANE-Rough | 7/9/2024 | Approved | SEAN HAUPT |
| Insulation | 7/17/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 7/23/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 7/24/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/28/2024 | Approved | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/30/2024 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 9/30/2024 | Conditional Approval | ARAM AVEDISIAN |
| Final | 10/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 10/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 10/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/31/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 10/31/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 10/31/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 11/8/2024 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 11/8/2024 | Approved | MEL KHACHATOURIAN |
| Final | 12/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Final | 12/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 12/12/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 12/12/2024 | Approved | ARAM AVEDISIAN |