4985 N GLEN IRIS AVE 90041
Certificate Information: 4985 N GLEN IRIS AVE 90041
- Application / Permit
- 22016-10000-18892
- Plan Check / Job No.
- B22LA12190
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing detached garage to new a.d.u per ordinance.
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2022 | MICHAEL LOPEZ |
| Corrections Issued | 7/12/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 7/24/2022 | MICHAEL LOPEZ |
| Issued | 8/1/2022 | APPLICANT |
| CofO in Progress | 8/3/2024 | CRAIG VAUGHAN |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/19/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 7/19/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Pre-Inspection | 12/29/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 1/3/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 1/17/2023 | Partial Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 2/7/2023 | Corrections Issued | RUBEN SALAS |
| Pre-Inspection | 5/31/2023 | Partial Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/15/2023 | Partial Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/29/2023 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/2/2023 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 10/2/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/5/2023 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 12/5/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/9/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/9/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 1/9/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/9/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/10/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/10/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/26/2024 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/26/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/27/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/29/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/17/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/17/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/20/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/10/2024 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 6/10/2024 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/10/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | CRAIG VAUGHAN |
| Final | 8/2/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 8/2/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/2/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Not Required | CRAIG VAUGHAN |