1087 S BROXTON AVE 90024
Certificate Information: 1087 S BROXTON AVE 90024
- Application / Permit
- 22016-10000-18682
- Plan Check / Job No.
- B22LA12018
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Sound Stage
- Work Description
- ePlan Change of Use portion of building from Retail to Retail/Sound stage (no audience) and TI. New stages/platforms, stairs, ramps, restrooms, exterior doors and stairs, ceiling pipe grid.
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/12/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/12/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/14/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 11/15/2022 | FARSHAD ALIMOHAMADI |
| Issued | 11/16/2022 | APPLICANT |
| CofO in Progress | 7/2/2024 | RICARDO ROBLES |
| Permit Finaled | 7/3/2024 | DAVID TSAU |
| CofO Issued | 7/3/2024 | DAVID TSAU |
| Permit Finaled | 7/3/2024 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 6/28/2022 | DONALD CRICHLOW |
| "D" conditions | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 7/15/2022 | NATHAN ROMINE |
| ZA Case | Cleared | 7/15/2022 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 7/19/2022 | JENSON LEE |
| Specific Plan | Cleared | 7/22/2022 | KEVIN FULTON |
| Specific Plan | Cleared | 7/22/2022 | KEVIN FULTON |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | JENSON LEE |
| DAS Clearance | Cleared | 9/21/2022 | Hernan Arreola |
| Specific Plan | Cleared | 10/17/2022 | PEDRO AYALA |
| Fire Marshal Fire Life Safety | Cleared | 10/19/2022 | MENOA AGHAJANI |
| Motion picture studio | Cleared | 10/19/2022 | MENOA AGHAJANI |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: NA27915 | , |
| Contractor | Dgr Construction Company Inc; Lic. No.: 1010921-B | , |
| Contractor | Primus Contractors; Lic. No.: 1010921-B | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: NA5593 | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/28/2022 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/6/2023 | Conditional Approval | PAUL DAVIDSON |
| Pre-Inspection | 3/10/2023 | Approved | PAUL DAVIDSON |
| Green Building Rough | 5/15/2023 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 5/15/2023 | Approved | PAUL DAVIDSON |
| Wood Frame | 5/15/2023 | Partial Inspection | PAUL DAVIDSON |
| Wood Frame | 5/19/2023 | Approved | PAUL DAVIDSON |
| Light Gage Steel Frame | 6/22/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 6/28/2023 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 7/14/2023 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 9/28/2023 | Partial Approval | PAUL DAVIDSON |
| T-Bar Ceiling | 9/28/2023 | Approved | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/6/2023 | Approved | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | PAUL DAVIDSON |
| Light Gage Steel Frame | 11/1/2023 | Approved | CASIMIR BRITTON |
| Deputy Drilled-In Anchors | 11/8/2023 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Approved | MICHAEL PETRUSKO |
| Special/Order Compliance | 12/12/2023 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 12/20/2023 | Corrections Issued | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Partial Approval | RICARDO ROBLES |
| Reinforced Concrete Frame | 4/4/2024 | Partial Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 4/5/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Final | 5/22/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Final | 5/22/2024 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 5/22/2024 | Approved | RICARDO ROBLES |
| Final | 7/2/2024 | OK to Issue CofO | RICARDO ROBLES |