21 1/4-1/2 W LIGHTHOUSE ST 90292

Certificate Information: 21 1/4-1/2 W LIGHTHOUSE ST 90292

Application / Permit
22016-10000-18667
Plan Check / Job No.
B22LA12005
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A (E)STORAGE AREA AND A (E) PARKING SPACE INTO A 319.65 SQ FT ADU IN EXISTING TWO STORY SINGLE FAMILY DEWLLING WITH ATTACHED GARAGE ( REAR UNIT ) (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e))
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
CofO Issued on 2/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 AUNG SOE
Corrections Issued 6/28/2022 AUNG SOE
Building Plans Picked Up 7/1/2022 APPLICANT
Plan Check Approved 9/27/2022 MINA HABILI
Issued 10/31/2022 APPLICANT
CofO in Progress 2/13/2024 HERBERT GIRON
Permit Finaled 2/20/2024 DANIEL ORRANTE
CofO Issued 2/20/2024 DANIEL ORRANTE
Permit Finaled 2/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 7/6/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 7/7/2022 JENSON LEE
Specific Plan Cleared 7/18/2022 PEDRO AYALA
Specific Plan Cleared 7/18/2022 PEDRO AYALA
Address approval Cleared 8/12/2022 HISASHI KOBAYAKAWA
Coastal Zone Cleared 9/7/2022 DALIA MOKAYED
Coastal Zone Cleared 9/7/2022 DALIA MOKAYED
Miscellaneous Cleared 9/7/2022 DALIA MOKAYED
Miscellaneous Cleared 9/7/2022 DALIA MOKAYED
Miscellaneous Cleared 9/7/2022 DALIA MOKAYED
Specific Plan Cleared 9/7/2022 DALIA MOKAYED
Tenant Habitability Plan Cleared 9/27/2022 RICARDO BOHORQUEZ

Contact Information

Contractor D C O Real Estate Inc; Lic. No.: 1078972-B 415 AVONDALE AVE      LOS ANGELES, CA 90049
Engineer Sims,, Bradley; Lic. No.: C58238 5462 WINDWARD AVE      LONG BEACH, CA 90814

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2022 Partial Inspection DAVID FEILER
Pre-Inspection 3/14/2023 Approved EVAN COOPER
PLUMBING-Rough 3/28/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/22/2023 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 5/24/2023 Corrections Issued HERBERT GIRON
Underground Mechanical 7/12/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 9/18/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 9/18/2023 Corrections Issued HERBERT GIRON
Green Building Rough 9/18/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 9/18/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/18/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/29/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 9/29/2023 Approved HERBERT GIRON
Green Building Rough 9/29/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 9/29/2023 Approved HERBERT GIRON
PLUMBING-Rough 9/29/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/12/2023 Conditional Approval HERBERT GIRON
Green Building Rough 10/12/2023 Approved HERBERT GIRON
Insulation 10/12/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 10/12/2023 Partial Approval HERBERT GIRON
Drywall Nailing 10/20/2023 Partial Approval HERBERT GIRON
Insulation 10/20/2023 Approved HERBERT GIRON
Light Gage Steel Frame 10/20/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/25/2023 Approved HERBERT GIRON
Drywall Nailing 10/25/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 11/7/2023 Approved HERBERT GIRON
Final 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 12/22/2023 Approved JESUS RODRIGUEZ
Green Building Final 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 12/22/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 1/11/2024 Corrections Issued HERBERT GIRON
Final 1/11/2024 Corrections Issued HERBERT GIRON
HVAC-Final 1/11/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 1/11/2024 Approved HERBERT GIRON
ELECTRICAL-Final 1/26/2024 Approved HERBERT GIRON
Final 1/26/2024 Corrections Issued HERBERT GIRON
Green Building Final 1/26/2024 Approved HERBERT GIRON
HVAC-Final 1/26/2024 Approved HERBERT GIRON
Final 2/12/2024 OK to Issue CofO HERBERT GIRON