5005 S MCCONNELL AVE 90066
Certificate Information: 5005 S MCCONNELL AVE 90066
- Application / Permit
- 22016-10000-18568
- Plan Check / Job No.
- B22LA11935
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- ePlan. TI in existing manufacturing/warehouse/office space to include new lab/R&D spaces and partitions. No change in existing use nor parking spaces.
- Permit Issued
- Issued on 10/10/2022
- Issuing Office
- Current Status
- CofO Issued on 9/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | TU HUA |
| Corrections Issued | 8/3/2022 | TU HUA |
| Quality Review Completed | 8/5/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/31/2022 | TU HUA |
| Applicant returned to address corrections | 9/14/2022 | TU HUA |
| Applicant returned to address corrections | 9/16/2022 | TU HUA |
| Applicant returned to address corrections | 9/21/2022 | TU HUA |
| Plan Check Approved | 10/5/2022 | TU HUA |
| Issued | 10/10/2022 | APPLICANT |
| TCO Issued (Expire Date: 03-10-2024) | 9/12/2023 | DAVID TSAU |
| TCO Issued (Expire Date: 08-27-2024) | 2/29/2024 | HENRY BAGHDASSARIAN |
| Permit Finaled | 9/4/2024 | DAVID TSAU |
| CofO Issued | 9/4/2024 | DAVID TSAU |
| Permit Finaled | 9/4/2024 | DAVID TSAU |
Permit Application Clearance Information
| ZA Case | Cleared | 8/9/2022 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | CATHERINE ADROVER |
| DAS Clearance | Cleared | 9/6/2022 | Hernan Arreola |
| Miscellaneous | Cleared | 9/7/2022 | WILLIAM JOHNS |
| Green Code | Cleared | 10/4/2022 | AARON COSTA |
Contact Information
| Architect | Friedman,, David; Lic. No.: NA12791 | , |
| Contractor | Worksmart Design; Lic. No.: 983360-B | , |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2022 | Approved | GRANT WOODS |
| Drywall Nailing | 11/15/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 11/15/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 11/22/2022 | Not Ready for Inspection | DAVID TSAU |
| Insulation | 11/22/2022 | Partial Approval | DAVID TSAU |
| Light Gage Steel Frame | 11/22/2022 | Partial Approval | DAVID TSAU |
| Drywall Nailing | 12/12/2022 | Partial Approval | GRANT WOODS |
| Insulation | 12/12/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 12/15/2022 | Partial Approval | AMANUEL BERHE |
| Drywall Nailing | 12/20/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 12/29/2022 | Partial Inspection | GRANT WOODS |
| Drywall Nailing | 1/13/2023 | Partial Approval | GRANT WOODS |
| Insulation | 2/9/2023 | Approved | AMANUEL BERHE |
| Drywall Nailing | 2/14/2023 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 2/14/2023 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 3/29/2023 | Partial Inspection | AMANUEL BERHE |
| T-Bar Ceiling | 4/7/2023 | Partial Inspection | GRANT WOODS |
| T-Bar Ceiling | 4/12/2023 | Conditional Approval | AMANUEL BERHE |
| Light Gage Steel Frame | 4/28/2023 | Approved | AMANUEL BERHE |
| Pre-Inspection | 5/19/2023 | Partial Inspection | GRANT WOODS |
| Deputy Pre-Stress Concrete | 6/2/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/6/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/8/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/9/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/12/2023 | Conditional Approval | GRANT WOODS |
| Deputy Wood Construction | 6/13/2023 | Conditional Approval | GRANT WOODS |
| Special/Order Compliance | 6/21/2023 | Partial Inspection | GRANT WOODS |
| Final | 8/10/2023 | Partial Inspection | GRANT WOODS |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Final | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Rough | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| Reinforced Masonry Frame | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 8/16/2023 | Conditional Approval | GRANT WOODS |
| Final | 8/16/2023 | Partial Inspection | GRANT WOODS |
| Green Building Final | 8/16/2023 | Not Ready for Inspection | GRANT WOODS |
| Green Building Rough | 8/16/2023 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Final | 8/16/2023 | Approved | GRANT WOODS |
| METHANE-Rough | 8/16/2023 | Approved | GRANT WOODS |
| Reinforced Masonry Frame | 8/16/2023 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/16/2023 | Not Ready for Inspection | GRANT WOODS |
| Special/Order Compliance | 2/13/2024 | Corrections Issued | GRANT WOODS |
| Special/Order Compliance | 7/31/2024 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 8/8/2024 | Conditional Approval | GRANT WOODS |
| Final | 8/28/2024 | Conditional Approval | GRANT WOODS |
| Green Building Final | 8/28/2024 | Approved | GRANT WOODS |
| Green Building Rough | 8/28/2024 | Approved | GRANT WOODS |
| Reinforced Masonry Frame | 8/28/2024 | Approved | GRANT WOODS |
| Smoke Detectors | 8/28/2024 | Approved | GRANT WOODS |