- Work Description
- ePlan - Exterior and Interior Remodel of (E) 2-story SFD including Remodel kitchen, Remove pocket door between kitchen and dining room, Remodel bathrooms, Add new closets, Relocate washer and dryer, close exterior door add interior swing door. All work per WFPP.
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/2/2023
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | MINA HABILI |
| Corrections Issued | 6/27/2022 | MINA HABILI |
| Applicant returned to address corrections | 7/11/2022 | MINA HABILI |
| Applicant returned to address corrections | 8/15/2022 | MINA HABILI |
| Plan Check Approved | 8/22/2022 | JOSEPH RAFOLS |
| No Progress | 9/6/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 9/6/2022 | JOSEPH RAFOLS |
| Issued | 9/6/2022 | APPLICANT |
| Permit Finaled | 3/1/2023 | ASHLEY THOMPSON |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/11/2022 | CONNIE CHAUV |
Contact Information
| Contractor | C S General Contracting Inc; Lic. No.: 947524-B | , |
| Engineer | Farah,, Moheb Dawod; Lic. No.: NA51477 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/5/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/6/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/6/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/7/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 11/7/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 11/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/10/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 11/10/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Shower Pan | 11/30/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/16/2023 | Corrections Issued | ASHLEY THOMPSON |
| Final | 2/16/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| MERV13>=Final | 2/16/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 2/16/2023 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 2/16/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/1/2023 | Approved | ASHLEY THOMPSON |
| Final | 3/1/2023 | Permit Finaled | ASHLEY THOMPSON |
| PLUMBING-Final | 3/1/2023 | Approved | ASHLEY THOMPSON |