1054-1058 W 79TH ST 90044
Certificate Information: 1054-1058 W 79TH ST 90044
- Application / Permit
- 22016-10000-18166
- Plan Check / Job No.
- B22LA11648
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) DEN TO BE CONVERTED INTO (N) ADU AND ATTACHED GARAGE TO BE CONVERTED TO (N) JR ADU TO (E) SFD
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | FERNANDO FLORES |
| Corrections Issued | 6/18/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Applicant returned to address corrections | 8/31/2022 | MINA HABILI |
| Plan Check Approved | 9/12/2022 | MINA HABILI |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 8/30/2023 | MICHAEL LEWIS |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/25/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | JEANETTE VONG |
| Miscellaneous | Cleared | 7/27/2022 | NOAH MCCOY |
| Community Plan Implem. Overlay | Cleared | 8/24/2022 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 12/1/2022 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 1/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 1/6/2023 | Approved | LILIANA PORTILLO |
| Wood Frame | 1/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/11/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 1/11/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 2/17/2023 | Approved | JOHN KLARIN |
| Masonry Wall/Backfill | 2/17/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 2/17/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 2/23/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/23/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 2/23/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/27/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 3/10/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 3/10/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/14/2023 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/14/2023 | Approved | LILIANA PORTILLO |
| Insulation | 3/17/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/21/2023 | Approved | LILIANA PORTILLO |
| Insulation | 3/21/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/28/2023 | Approved | LILIANA PORTILLO |
| Final | 6/28/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 6/28/2023 | Approved | MICHAEL LEWIS |
| Final | 7/18/2023 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/18/2023 | SGSOV Approved | MICHAEL LEWIS |
| Final | 8/29/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 8/29/2023 | Approved | MICHAEL LEWIS |