1054-1058 W 79TH ST 90044

Certificate Information: 1054-1058 W 79TH ST 90044

Application / Permit
22016-10000-18166
Plan Check / Job No.
B22LA11648
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) DEN TO BE CONVERTED INTO (N) ADU AND ATTACHED GARAGE TO BE CONVERTED TO (N) JR ADU TO (E) SFD
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 FERNANDO FLORES
Corrections Issued 6/18/2022 FERNANDO FLORES
Building Plans Picked Up 7/7/2022 APPLICANT
Applicant returned to address corrections 8/31/2022 MINA HABILI
Plan Check Approved 9/12/2022 MINA HABILI
Issued 9/12/2022 APPLICANT
CofO in Progress 8/30/2023 MICHAEL LEWIS
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/25/2022 JEANETTE VONG
Sewer availability Cleared 7/25/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/26/2022 JEANETTE VONG
Miscellaneous Cleared 7/27/2022 NOAH MCCOY
Community Plan Implem. Overlay Cleared 8/24/2022 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2022 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 12/1/2022 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 12/5/2022 Corrections Issued LILIANA PORTILLO
Wood Frame 1/3/2023 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 1/6/2023 Approved LILIANA PORTILLO
Wood Frame 1/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/11/2023 Partial Approval LILIANA PORTILLO
Insulation 1/11/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/17/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 2/17/2023 Approved JOHN KLARIN
Masonry Wall/Backfill 2/17/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 2/17/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 2/23/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/23/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 2/23/2023 Approved LILIANA PORTILLO
HVAC-Rough 2/27/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/10/2023 Approved LILIANA PORTILLO
Shower Pan 3/10/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/14/2023 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 3/14/2023 Approved LILIANA PORTILLO
Insulation 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 3/21/2023 Approved LILIANA PORTILLO
Insulation 3/21/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/28/2023 Approved LILIANA PORTILLO
Final 6/28/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 6/28/2023 Approved MICHAEL LEWIS
Final 7/18/2023 Partial Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved MICHAEL LEWIS
Final 8/29/2023 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 8/29/2023 Approved MICHAEL LEWIS