1261 1/2 W 81ST ST 90044

Certificate Information: 1261 1/2 W 81ST ST 90044

Application / Permit
22016-10000-18064
Plan Check / Job No.
B22LA11559
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A). WORK PER WFPP
Permit Issued
Issued on 9/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/15/2022 RACHEL BEYENE
Corrections Issued 6/15/2022 RACHEL BEYENE
Applicant returned to address corrections 7/7/2022 RACHEL BEYENE
Plan Check Approved 9/2/2022 ADAM HEGAZI
Plan Check Approved 9/2/2022 ADAM HEGAZI
Issued 9/6/2022 APPLICANT
CofO in Progress 7/12/2023 STUART CHAPMAN
Permit Finaled 7/20/2023 DEROLD HAUFF
CofO Issued 7/20/2023 DEROLD HAUFF
Permit Finaled 7/20/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/11/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/11/2022 JEANIE LAM
Sewer availability Cleared 7/11/2022 JEANIE LAM
Community Plan Implem. Overlay Cleared 8/31/2022 TINA MIRANDA
Construction near power lines Cleared 8/31/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2022 Partial Inspection LILIANA PORTILLO
Pre-Inspection 11/14/2022 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 12/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/29/2022 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 1/6/2023 Approved MICHAEL LEWIS
Underground Mechanical 1/6/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 2/10/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 2/10/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 2/10/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/15/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 2/15/2023 Approved LILIANA PORTILLO
HVAC-Rough 2/15/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/15/2023 Approved LILIANA PORTILLO
Sewer 2/15/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/23/2023 Approved LILIANA PORTILLO
HVAC-Rough 2/23/2023 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 2/23/2023 Corrections Issued LILIANA PORTILLO
Insulation 3/1/2023 Corrections Issued LILIANA PORTILLO
Underground Mechanical 3/1/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 3/6/2023 Approved LILIANA PORTILLO
Insulation 3/6/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/16/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/16/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 6/2/2023 Not Ready for Inspection STUART CHAPMAN
Final 6/2/2023 Corrections Issued STUART CHAPMAN
HVAC-Final 6/2/2023 Approved STUART CHAPMAN
PLUMBING-Final 6/2/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 7/12/2023 Approved STUART CHAPMAN
Final 7/12/2023 OK to Issue CofO STUART CHAPMAN
Service/Power Release 7/12/2023 Approved STUART CHAPMAN