139-139 1/2 E 51ST ST 90011

Certificate Information: 139-139 1/2 E 51ST ST 90011

Application / Permit
22016-10000-17982
Plan Check / Job No.
B22LA11512
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TO CONVERT AN EXISTING STORAGE ROOM INTO ADU IN EXISTING 2 SOTRY RESIDENTIAL BUILDING (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 11/17/2022
Issuing Office
Metro
Current Status
Issued on 11/17/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/15/2022 JOSEPH RAFOLS
Corrections Issued 6/16/2022 JOSEPH RAFOLS
Building Plans Picked Up 6/21/2022 APPLICANT
Applicant returned to address corrections 7/1/2022 KHUONG TRUONG
Plan Check Approved 9/21/2022 AUNG SOE
Issued 11/17/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/7/2022 STEVE MELGAR
Sewer availability Cleared 7/7/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/8/2022 JEANIE LAM
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/2/2022 No Access for Inspection JULIAN AMAYA
BUILDING-Rough-Frame 12/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 12/15/2023 Approved ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 1/19/2024 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/29/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/22/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/25/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 11/25/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/10/2025 Conditional Approval RONNIE MEDINA
ELECTRICAL-Rough 9/10/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 9/10/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/12/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/12/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/12/2025 Approved ALEJANDRO DE ARTOLA
Insulation 9/12/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/12/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/6/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 10/6/2025 Partial Approval RONNIE MEDINA
Interior/Exterior Lathing 1/15/2026 Partial Approval ALEJANDRO DE ARTOLA