12926 W VENICE BLVD 90066
Certificate Information: 12926 W VENICE BLVD 90066
- Application / Permit
- 22016-10000-17976
- Plan Check / Job No.
- B22LA11508
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use from Dance Studio to Restaurant. Hours of operation are from 11am-11pm.
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | SALVADOR QUINTANILLA |
| Corrections Issued | 6/14/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/28/2022 | SALVADOR QUINTANILLA |
| Plan Check Approved | 7/26/2022 | SALVADOR QUINTANILLA |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 3/23/2023 | SORIN CIRSTOIU |
| Permit Finaled | 3/23/2023 | DAVID TSAU |
| CofO Issued | 3/23/2023 | DAVID TSAU |
| Permit Finaled | 3/23/2023 | DAVID TSAU |
Permit Application Clearance Information
| Food establishment approval | Cleared | 6/14/2022 | LACDHS APPROVED |
| "Q" conditions | Cleared | 6/22/2022 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 6/22/2022 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 7/1/2022 | RYAN LY |
| Specific Plan | Cleared | 7/6/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/7/2022 | DINAH GARIN |
| Food Service Establishment | Cleared | 7/20/2022 | KENNETH BROWNE |
Contact Information
| Contractor | Custom Interior Solutions Inc; Lic. No.: 1094565-B | 4125 INGLEWOOD BLVD 7 LOS ANGELES, CA 90066 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2022 | Not Ready for Inspection | NICK LAROCCA |
| Pre-Inspection | 8/9/2022 | No Access for Inspection | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | No Access for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 8/11/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wall Anchors | 8/19/2022 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 8/19/2022 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 10/3/2022 | Not Ready for Inspection | NICK LAROCCA |
| Wall Anchors | 10/4/2022 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 10/4/2022 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 10/17/2022 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 1/18/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 1/18/2023 | Not Ready for Inspection | GRANT WOODS |
| Final | 2/6/2023 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 2/6/2023 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 2/6/2023 | Partial Inspection | SORIN CIRSTOIU |
| T-Bar Ceiling | 2/24/2023 | Corrections Issued | AMANUEL BERHE |
| Final | 3/6/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | AMANUEL BERHE |
| Smoke Detectors | 3/6/2023 | Approved | AMANUEL BERHE |
| T-Bar Ceiling | 3/6/2023 | Approved | AMANUEL BERHE |
| Final | 3/13/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 3/17/2023 | Conditional Approval | AMANUEL BERHE |
| Final | 3/23/2023 | OK to Issue CofO | SORIN CIRSTOIU |