5643 1/2 W WENLOCK ST 90016

Certificate Information: 5643 1/2 W WENLOCK ST 90016

Application / Permit
22016-10000-17973
Plan Check / Job No.
B22LA11505
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
A CONVERSION OF AN EXISTING DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT. ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/15/2022 JOSEPH RAFOLS
Corrections Issued 6/16/2022 JOSEPH RAFOLS
Building Plans Picked Up 6/30/2022 APPLICANT
Plan Check Approved 9/19/2022 JAD BASMA
Issued 9/26/2022 APPLICANT
CofO in Progress 12/15/2023 DEROLD HAUFF
CofO Issued 12/15/2023 DEROLD HAUFF
Permit Finaled 12/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/20/2022 RIDWAN HARDY
Address approval Cleared 8/30/2022 WALLIE JONG
Sewer availability Cleared 8/30/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/31/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/7/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/13/2023 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/13/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 4/13/2023 Approved ANTHONY EGSON
METHANE-Rough 4/13/2023 Approved ANTHONY EGSON
PLUMBING-Rough 4/13/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 5/2/2023 Corrections Issued ANTHONY EGSON
Insulation 5/2/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 5/2/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 5/10/2023 Approved ANTHONY EGSON
HVAC-Rough 5/10/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 5/10/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 5/16/2023 Approved ANTHONY EGSON
Drywall Nailing 5/16/2023 Approved ANTHONY EGSON
Insulation 5/16/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/16/2023 Approved ANTHONY EGSON
PLUMBING-Rough 5/16/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/1/2023 Approved ANTHONY EGSON
Final 7/19/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 7/19/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 8/10/2023 Corrections Issued ANTHONY EGSON
Final 8/10/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 8/10/2023 Approved ANTHONY EGSON
PLUMBING-Final 8/10/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 8/24/2023 Approved STUART CHAPMAN
Final 8/24/2023 Conditional Approval STUART CHAPMAN
Final 12/6/2023 OK to Issue CofO STUART CHAPMAN
Service/Power Release 12/6/2023 Approved STUART CHAPMAN