4215 S GLENCOE AVE 90292
Certificate Information: 4215 S GLENCOE AVE 90292
- Application / Permit
- 22016-10000-17909
- Plan Check / Job No.
- B22LA11463
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- INSTALL (NEW) SAFETY PARAPET WALL AROUND PERIMETER OF (E) ROOFTOP (no change in building height)
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/2/2025
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | SHAHEN AKELYAN |
| Corrections Issued | 6/21/2022 | ZAW HAN |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Plan Check Approved | 7/6/2022 | AUNG SOE |
| Plan Check Approved | 8/26/2022 | RICARDO RAMIREZ |
| Issued | 1/23/2023 | APPLICANT |
| Permit Finaled | 8/29/2025 | VASIL MIHALEV |
Permit Application Clearance Information
| "D" conditions | Cleared | 6/28/2022 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 6/28/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 6/28/2022 | DALIA MOKAYED |
Contact Information
| Architect | Althaus,, Andrew Ernst; Lic. No.: C25002 | 31368 VIA COLINAS #105 WESTLAKE VILLAGE, CA 91362 |
| Contractor | J P Builders & Development Inc; Lic. No.: 992192-B | P O BOX 5366 SHERMAN OAKS, CA 91413 |
| Engineer | Garcia,, Ramon; Lic. No.: S4595 | 732 HOLBERTSON COURT SIMI VALLEY, CA 93065 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 5/18/2023 | Partial Inspection | GRANT WOODS |
| Wood Frame | 5/30/2023 | Partial Approval | GRANT WOODS |
| Wood Frame | 6/20/2023 | Partial Approval | GRANT WOODS |
| Wood Frame | 7/10/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 7/19/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 8/15/2023 | Partial Inspection | GRANT WOODS |
| Wood Frame | 9/5/2023 | No Access for Inspection | GRANT WOODS |
| Final | 8/29/2025 | Permit Finaled | VASIL MIHALEV |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | VASIL MIHALEV |
| Smoke Detectors | 8/29/2025 | Approved | VASIL MIHALEV |