3204-3206 W 27TH ST 90018
Certificate Information: 3204-3206 W 27TH ST 90018
- Application / Permit
- 22016-10000-17891
- Plan Check / Job No.
- B22LA11445
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) FAMILY ROOM & 1-CAR GARAGE TO AN ATTACHED ADU (3204 1/2 W 27TH ST 703 SF) PER ORDINANCE AND LAMC 12.22 A33(c)&(e). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | ZAW HAN |
| Corrections Issued | 6/14/2022 | ZAW HAN |
| Plan Check Approved | 9/9/2022 | ADAM HEGAZI |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | CALEB MEISTER |
| Permit Finaled | 8/16/2023 | DEROLD HAUFF |
| CofO Issued | 8/16/2023 | DEROLD HAUFF |
| Permit Finaled | 8/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 7/19/2022 | AMANDA KAINER |
| Address approval | Cleared | 8/1/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/1/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 8/1/2022 | TREVOR QUAN |
| Tenant Habitability Plan | Cleared | 8/24/2022 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/24/2023 | Corrections Issued | CALEB MEISTER |
| Wood Frame | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 3/2/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 3/2/2023 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 3/2/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/7/2023 | Conditional Approval | CALEB MEISTER |
| HVAC-Rough | 3/7/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 3/7/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | CALEB MEISTER |
| Insulation | 4/3/2023 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 4/3/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 4/3/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 4/18/2023 | Approved | STUART CHAPMAN |
| Insulation | 4/18/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/18/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/13/2023 | Corrections Issued | CALEB MEISTER |
| Final | 6/13/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 6/13/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 6/13/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 6/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 6/13/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 7/7/2023 | Approved | CALEB MEISTER |
| Final | 7/7/2023 | OK to Issue CofO | CALEB MEISTER |