829 W 134TH ST 90247

Certificate Information: 829 W 134TH ST 90247

Application / Permit
22016-10000-17669
Plan Check / Job No.
B22LA11281
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED GARAGE INTO ADU PER ORDINANCE.
Permit Issued
Issued on 3/4/2023
Issuing Office
Current Status
CofO Issued on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 FARSHAD ALIMOHAMADI
Corrections Issued 7/29/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 2/26/2023 FARSHAD ALIMOHAMADI
Issued 3/4/2023 APPLICANT
CofO in Progress 10/20/2023 JOHN KLARIN
CofO Issued 10/20/2023 ANSON MAGLASANG
Permit Finaled 10/20/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/1/2022 ERIK BEASLEY
Sewer availability Cleared 9/1/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/26/2022 ERIK BEASLEY
Construction near power lines Cleared 2/14/2023 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2023 Approved JAMES CHAVEZ
Underground Mechanical 5/30/2023 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 6/21/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 6/21/2023 Corrections Issued JAMES CHAVEZ
Wood Frame 6/21/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 6/26/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 6/26/2023 Approved JAMES CHAVEZ
HVAC-Rough 6/29/2023 Approved JAMES CHAVEZ
Insulation 7/3/2023 Approved JAMES CHAVEZ
Drywall Nailing 7/5/2023 Approved JAMES CHAVEZ
Shower Pan 7/11/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/14/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 9/26/2023 Approved JAMES CHAVEZ
Final 9/26/2023 Corrections Issued JAMES CHAVEZ
METHANE-Final 9/26/2023 Approved JAMES CHAVEZ
METHANE-Rough 9/26/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 9/26/2023 Approved JAMES CHAVEZ
Final 10/5/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Final 10/19/2023 Approved JOHN KLARIN
Final 10/19/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 10/19/2023 Approved JOHN KLARIN
PLUMBING-Final 10/19/2023 Approved JOHN KLARIN