829 W 134TH ST 90247
Certificate Information: 829 W 134TH ST 90247
- Application / Permit
- 22016-10000-17669
- Plan Check / Job No.
- B22LA11281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT EXISTING DETACHED GARAGE INTO ADU PER ORDINANCE.
- Permit Issued
- Issued on 3/4/2023
- Issuing Office
- Current Status
- CofO Issued on 10/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/29/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/26/2023 | FARSHAD ALIMOHAMADI |
| Issued | 3/4/2023 | APPLICANT |
| CofO in Progress | 10/20/2023 | JOHN KLARIN |
| CofO Issued | 10/20/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/20/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/1/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | ERIK BEASLEY |
| Construction near power lines | Cleared | 2/14/2023 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 5/30/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/21/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 6/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Wood Frame | 6/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/26/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/26/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 6/29/2023 | Approved | JAMES CHAVEZ |
| Insulation | 7/3/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/5/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 7/11/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/14/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | JAMES CHAVEZ |
| Final | 9/26/2023 | Corrections Issued | JAMES CHAVEZ |
| METHANE-Final | 9/26/2023 | Approved | JAMES CHAVEZ |
| METHANE-Rough | 9/26/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 9/26/2023 | Approved | JAMES CHAVEZ |
| Final | 10/5/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/19/2023 | Approved | JOHN KLARIN |
| Final | 10/19/2023 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 10/19/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/19/2023 | Approved | JOHN KLARIN |