2723 E PEPPER AVE 90065
Certificate Information: 2723 E PEPPER AVE 90065
- Application / Permit
- 22016-10000-17539
- Plan Check / Job No.
- B22LA11194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. 19X18 GARAGE TO ADU STATE LAW ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | KHUONG TRUONG |
| Corrections Issued | 6/9/2022 | KHUONG TRUONG |
| Plan Check Approved | 7/14/2022 | DANIEL SANJUAN |
| Issued | 7/14/2022 | APPLICANT |
| CofO in Progress | 7/27/2023 | ALIZAH MAYAGOITIA |
| CofO Issued | 8/7/2023 | DEROLD HAUFF |
| Permit Finaled | 8/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/17/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2022 | AMAAN MALIK |
| Supp. Use District POD/CDO/TDO | Cleared | 7/14/2022 | NASHYA JENSEN |
Contact Information
| Contractor | Mdr Builders; Lic. No.: 741228-B | 342 S GERHART AVE LOS ANGELES, CA 90022 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/28/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/29/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 9/29/2022 | Partial Inspection | OSVALDO PARAMO |
| Sewer | 9/29/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/3/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/13/2022 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 10/13/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 11/3/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/3/2022 | Partial Approval | OSVALDO PARAMO |
| Insulation | 11/10/2022 | Approved | OSVALDO PARAMO |
| Shower Pan | 11/10/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/16/2022 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 12/1/2022 | Approved | OSVALDO PARAMO |
| Final | 7/11/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/11/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/11/2023 | Approved | OSVALDO PARAMO |
| Final | 7/17/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/26/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/26/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/26/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/26/2023 | Approved | ALIZAH MAYAGOITIA |