204 E 80TH ST 90003
Certificate Information: 204 E 80TH ST 90003
- Application / Permit
- 22016-10000-17497
- Plan Check / Job No.
- B22LA11161
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO (N) ADU
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | MINA HABILI |
| Corrections Issued | 6/9/2022 | MINA HABILI |
| Plan Check Approved | 6/21/2022 | FERNANDO FLORES |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 4/5/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/8/2025 | DEROLD HAUFF |
| CofO Issued | 4/8/2025 | DEROLD HAUFF |
| Permit Finaled | 4/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/14/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 9/13/2022 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 9/23/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/3/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/3/2022 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 10/6/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 10/12/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/12/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/19/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/19/2022 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 10/19/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 10/25/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/25/2022 | Approved | LILIANA PORTILLO |
| Insulation | 10/27/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/27/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 11/7/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 1/4/2023 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 1/4/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/4/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/6/2023 | Approved | LILIANA PORTILLO |
| Final | 3/6/2023 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 3/6/2023 | Not Required | LILIANA PORTILLO |
| Final | 4/4/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |