204 E 80TH ST 90003

Certificate Information: 204 E 80TH ST 90003

Application / Permit
22016-10000-17497
Plan Check / Job No.
B22LA11161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO (N) ADU
Permit Issued
Issued on 8/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 MINA HABILI
Corrections Issued 6/9/2022 MINA HABILI
Plan Check Approved 6/21/2022 FERNANDO FLORES
Issued 8/23/2022 APPLICANT
CofO in Progress 4/5/2025 ALEJANDRO DE ARTOLA
Permit Finaled 4/8/2025 DEROLD HAUFF
CofO Issued 4/8/2025 DEROLD HAUFF
Permit Finaled 4/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/14/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/14/2022 JEANIE LAM
Sewer availability Cleared 6/14/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 9/13/2022 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 9/23/2022 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 10/3/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/3/2022 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 10/6/2022 Approved HORACE FULTZ
Footing/Foundation/Slab 10/12/2022 Approved LILIANA PORTILLO
Underground Mechanical 10/12/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/19/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved LILIANA PORTILLO
HVAC-Rough 10/19/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 10/19/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/25/2022 Approved LILIANA PORTILLO
Green Building Rough 10/25/2022 Approved LILIANA PORTILLO
HVAC-Rough 10/25/2022 Approved LILIANA PORTILLO
Insulation 10/27/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/27/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 11/7/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Final 1/4/2023 Corrections Issued LILIANA PORTILLO
Gas Test 1/4/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 1/4/2023 Approved LILIANA PORTILLO
HVAC-Final 1/4/2023 Approved LILIANA PORTILLO
PLUMBING-Final 1/4/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/4/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/6/2023 Approved LILIANA PORTILLO
Final 3/6/2023 Corrections Issued LILIANA PORTILLO
Service/Power Release 3/6/2023 Not Required LILIANA PORTILLO
Final 4/4/2025 OK to Issue CofO ALEJANDRO DE ARTOLA