6652 1/2 E HOUGH ST 90042

Certificate Information: 6652 1/2 E HOUGH ST 90042

Application / Permit
22016-10000-17480
Plan Check / Job No.
B22LA11137
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX GARAGE TO ADU
Permit Issued
Issued on 9/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 JAD BASMA
Corrections Issued 6/25/2022 JAD BASMA
Building Plans Picked Up 7/12/2022 APPLICANT
Plan Check Approved 9/20/2022 JAD BASMA
Issued 9/28/2022 APPLICANT
CofO in Progress 4/27/2026 DAVID WILLIAMS
No Progress 4/27/2026 CHARLES BOGHOSKHAN
CofO in Progress 4/27/2026 CHARLES BOGHOSKHAN
CofO in Progress 4/28/2026 DAVID WILLIAMS
CofO in Progress 5/20/2026 DAVID WILLIAMS
CofO Issued 5/21/2026 DEROLD HAUFF
Permit Finaled 5/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/20/2022 JEANIE LAM
Sewer availability Cleared 7/20/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/21/2022 JEANIE LAM
Hydrant and Access approval Cleared 9/13/2022 KURT CORRAL
Grading Pre-Inspection Cleared 9/20/2022 JAD BASMA

Contact Information

Contractor Mdr Builders; Lic. No.: 741228-B 342 S GERHART AVE      LOS ANGELES, CA 90022
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2022 Approved AMY COLIN
Footing/Foundation/Slab 10/26/2022 Approved AMY COLIN
Green Building Rough 11/16/2022 Not Ready for Inspection AMY COLIN
Wood Frame 11/16/2022 Conditional Approval AMY COLIN
Insulation 12/1/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 12/1/2023 Approved ROY SPAULDING
Drywall Nailing 12/8/2023 Approved ROY SPAULDING
Final 1/2/2024 No Access for Inspection ROY SPAULDING
Green Building Final 1/2/2024 No Access for Inspection ROY SPAULDING
Green Building Rough 1/2/2024 No Access for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 1/2/2024 No Access for Inspection ROY SPAULDING
Wood Frame 1/2/2024 No Access for Inspection ROY SPAULDING
Deputy Drilled-In Anchors 9/30/2024 Conditional Approval ALIZAH MAYAGOITIA
Final 3/4/2026 Corrections Issued DAVID WILLIAMS
Green Building Final 3/4/2026 Approved DAVID WILLIAMS
Green Building Rough 3/4/2026 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 3/4/2026 Approved DAVID WILLIAMS
Wood Frame 3/4/2026 Approved DAVID WILLIAMS
Final 3/24/2026 Corrections Issued DAVID WILLIAMS
Final 4/27/2026 Corrections Issued DAVID WILLIAMS
Final 5/20/2026 OK to Issue CofO DAVID WILLIAMS