6119 W 76TH ST 90045

Certificate Information: 6119 W 76TH ST 90045

Application / Permit
22016-10000-17475
Plan Check / Job No.
B22LA11134
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND (E) REC. ROOM INTO ADU 545 SQ FT PER WFPP (DETACHED/CONVERSION ADU PER GCS65852.2(e)(1)(A))
Permit Issued
Issued on 9/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 MINA HABILI
Corrections Issued 6/9/2022 MINA HABILI
Plan Check Approved 9/2/2022 DANIEL SANJUAN
Issued 9/7/2022 APPLICANT
CofO in Progress 5/22/2023 BOBBY KEY
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/11/2022 JOSE HERNANDEZ
Sewer availability Cleared 6/11/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 6/13/2022 JOSE HERNANDEZ
Specific Plan Cleared 8/16/2022 EDUARDO HERMOSO
Construction near power lines Cleared 8/31/2022 TINA MIRANDA
Grading Pre-Inspection Cleared 9/2/2022 MINA HABILI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/5/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 1/5/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 1/5/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 1/17/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 1/17/2023 Partial Approval BOBBY KEY
Final 1/17/2023 Corrections Issued BOBBY KEY
HVAC-Rough 1/17/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 1/17/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 1/17/2023 Partial Approval BOBBY KEY
HVAC-Rough 1/27/2023 Conditional Approval HERBERT GIRON
Insulation 1/27/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 2/7/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 2/7/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 2/7/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 2/14/2023 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 2/14/2023 Approved BOBBY KEY
Drywall Nailing 3/1/2023 Approved HERBERT GIRON
ELECTRICAL-Final 5/12/2023 Corrections Issued BOBBY KEY
Final 5/12/2023 Corrections Issued BOBBY KEY
HVAC-Final 5/12/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 5/12/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/12/2023 Approved BOBBY KEY
ELECTRICAL-Final 5/22/2023 Approved BOBBY KEY
Final 5/22/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 5/22/2023 Approved BOBBY KEY
PLUMBING-Final 5/22/2023 Approved BOBBY KEY