10759 W AYRES AVE 90064
Certificate Information: 10759 W AYRES AVE 90064
- Application / Permit
- 22016-10000-17438
- Plan Check / Job No.
- B22LA11097
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Garage - Public
- Work Description
- ePlan Building alteration to remove a portion of the existing parking structure. ***SEE COMMENTS***
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/6/2025
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | MICHAEL LOPEZ |
| Corrections Issued | 7/8/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 7/13/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/19/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 8/26/2022 | MICHAEL LOPEZ |
| Issued | 8/29/2022 | APPLICANT |
| Permit Finaled | 8/5/2025 | DERRICK SPENCER |
Permit Application Clearance Information
| ZA Case | Cleared | 7/12/2022 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 7/14/2022 | ORVAL HERNANDEZ-MARCI |
| Flood clearance | Cleared | 7/26/2022 | BRYAN GATHUKA |
| Green Code | Cleared | 7/26/2022 | DONALD CRICHLOW |
| Work Adjacent to Public Way | Cleared | 7/28/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 7/29/2022 | MICHAEL LOPEZ |
| DAS Clearance | Cleared | 8/4/2022 | OLLIE CARTER |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | DINAH GARIN |
| Specific Plan | Cleared | 8/11/2022 | CONNIE CHAUV |
Contact Information
| Contractor | Build Group Construction Company Inc; Lic. No.: 1015855-B | 1212 ABBOT KINNEY BLVD #A LOS ANGELES, CA 90291 |
| Engineer | , ; Lic. No.: NA3738 | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 11/15/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 11/15/2022 | Conditional Approval | DERRICK SPENCER |
| Piling/Pier/Caisson | 2/7/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Final | 6/26/2023 | Approved | DERRICK SPENCER |
| Final | 8/5/2025 | Permit Finaled | DERRICK SPENCER |
| METHANE-Final | 8/5/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 8/5/2025 | Approved | DERRICK SPENCER |