11460 N PORTER RANCH DR 91326

Certificate Information: 11460 N PORTER RANCH DR 91326

Application / Permit
22016-10000-17079
Plan Check / Job No.
B22LA10883
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT WORK FOR HARDWARE STORE (RETAIL). NEW SALES AREA, NEW INTERIOR PARTITIONS, EXISITING RESTROOMS AND OFFICE SPACES TO REMAIN. EXISITING HVAC UNITS AT ROOF TO REMAIN. NO CHANGE IN PARKING.
Permit Issued
Issued on 1/13/2023
Issuing Office
Valley
Current Status
Permit Finaled on 11/17/2023

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Disabled Access Plans Picked Up 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 ALBERT SERVIN
Corrections Issued 6/28/2022 ALBERT SERVIN
Quality Review Completed 6/29/2022 PETER KIM
Building Plans Picked Up 6/30/2022 APPLICANT
Applicant returned to address corrections 8/1/2022 ALBERT SERVIN
Green Plans Picked Up 8/1/2022 APPLICANT
Plan Check Approved 12/13/2022 ALBERT SERVIN
Issued 1/13/2023 APPLICANT
Permit Finaled 11/17/2023 DEANDRE HOFFMAN

Permit Application Clearance Information

Green Code Cleared 7/19/2022 DONALD CRICHLOW
DAS Clearance Cleared 7/21/2022 SHINE LIN
"D" conditions Cleared 7/27/2022 JAZMIN ROQUE
Grading Pre-Inspection Cleared 7/28/2022 KIRK LINKLATER
Specific Plan Cleared 11/22/2022 PEGGY MALONE-BROWN

Contact Information

Architect Malak,, Hany; Lic. No.: C27490 360 PINE TREE LANE      MONROVIA, CA 91016
Contractor Bccm Construciton Group Inc; Lic. No.: 1038967-B 100 E 7TH STREET SUITE 201      KANSAS CITY, MO 64106
Engineer Leonard,, Joseph Kristian; Lic. No.: S2969 106 W LIME STE 206B      MONROVIA, CA 91016

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/3/2023 Partial Inspection DEANDRE HOFFMAN
Structural Steel Frame 3/3/2023 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 3/6/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 3/14/2023 Partial Inspection DEANDRE HOFFMAN
Insulation 3/14/2023 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 3/14/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 3/15/2023 Conditional Approval DEANDRE HOFFMAN
Drywall Nailing 3/24/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/5/2023 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/6/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/13/2023 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/18/2023 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/20/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 4/25/2023 Conditional Approval DEANDRE HOFFMAN
Light Gage Steel Frame 4/26/2023 Partial Inspection DEANDRE HOFFMAN
T-Bar Ceiling 4/26/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 4/28/2023 Conditional Approval DEANDRE HOFFMAN
Reinforced Concrete Frame 4/28/2023 Partial Inspection DEANDRE HOFFMAN
T-Bar Ceiling 4/28/2023 Not Ready for Inspection DEANDRE HOFFMAN
Drywall Nailing 5/2/2023 Not Ready for Inspection DEANDRE HOFFMAN
Insulation 5/2/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 5/4/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 5/8/2023 Conditional Approval DEANDRE HOFFMAN
Structural Steel Frame 5/8/2023 Not Ready for Inspection DEANDRE HOFFMAN
Deputy Steel/Welding 5/10/2023 Conditional Approval DEANDRE HOFFMAN
Structural Steel Frame 5/10/2023 Not Ready for Inspection DEANDRE HOFFMAN
T-Bar Ceiling 5/10/2023 Partial Inspection DEANDRE HOFFMAN
Wall Anchors 5/10/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 5/11/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Shotcrete 5/11/2023 Conditional Approval DEANDRE HOFFMAN
Reinforced Concrete Frame 5/12/2023 Partial Inspection JEFFREY FULTON
Structural Steel Frame 5/12/2023 Not Ready for Inspection JEFFREY FULTON
T-Bar Ceiling 5/12/2023 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/13/2023 Partial Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/15/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 5/15/2023 Conditional Approval JEFFREY FULTON
T-Bar Ceiling 5/15/2023 Not Ready for Inspection JEFFREY FULTON
T-Bar Ceiling 5/15/2023 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 5/31/2023 Not Ready for Inspection DEANDRE HOFFMAN
T-Bar Ceiling 6/8/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 6/22/2023 Not Ready for Inspection DEANDRE HOFFMAN
Final 6/29/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Final 6/29/2023 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 6/29/2023 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 6/30/2023 Corrections Issued DEANDRE HOFFMAN
Special/Order Compliance 7/3/2023 Partial Inspection DEANDRE HOFFMAN
Final 7/4/2023 Off-Hour Fees Due
Green Building Final 7/4/2023 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/4/2023 Off-Hour Fees Due
Smoke Detectors 7/4/2023 Off-Hour Fees Due
Smoke Detectors 7/4/2023 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 7/4/2023 Partial Inspection DEANDRE HOFFMAN
Final 11/17/2023 Permit Finaled DEANDRE HOFFMAN
Green Building Final 11/17/2023 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 11/17/2023 Approved DEANDRE HOFFMAN