4601 W SUNSET BLVD 1st Floor 90027
Certificate Information: 4601 W SUNSET BLVD 1st Floor 90027
- Application / Permit
- 22016-10000-17075
- Plan Check / Job No.
- B22LA10881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ALTERATION TO OFFICES ON 1ST FLOOR: CONVERT EXISTING FILE ROOM TO THREE OFFICES SPACE AND ONE CONFERENCE ROOM .
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/23/2023
Permit Application Status History
| Submitted | 6/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2022 | ZAW HAN |
| Corrections Issued | 6/6/2022 | ZAW HAN |
| Plan Check Approved | 7/20/2022 | JESSE JIMENEZ |
| Issued | 9/20/2022 | APPLICANT |
| Permit Finaled | 2/6/2023 | TIMOTHY POWELL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/12/2022 | AMAAN MALIK |
| Specific Plan | Cleared | 7/15/2022 | DANALYNN DOMINGUEZ |
Contact Information
| Architect | Herman,, Richard Sigmund; Lic. No.: C9727 | 1725 GARDENA AVE. GLENDALE, CA 91204 |
| Contractor | Desai Construction & Developers Inc; Lic. No.: 855339-B | PO BOX 17307 ANAHEIM, CA 92817 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/25/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 12/2/2022 | No Access for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 12/2/2022 | No Access for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 12/2/2022 | No Access for Inspection | ALFREDO LOPEZ |
| Final | 12/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 12/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 12/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/16/2022 | No Access for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 12/16/2022 | Not Ready for Inspection | JONATHAN QUACH |
| T-Bar Ceiling | 12/19/2022 | Partial Approval | RONALD JIMENEZ |
| Final | 12/29/2022 | Corrections Issued | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 12/29/2022 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 12/29/2022 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 1/12/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| T-Bar Ceiling | 1/12/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 1/30/2023 | Partial Inspection | TIMOTHY POWELL |
| T-Bar Ceiling | 1/30/2023 | Approved | TIMOTHY POWELL |
| Final | 2/6/2023 | Permit Finaled | TIMOTHY POWELL |