7733 N HASKELL AVE 91406

Certificate Information: 7733 N HASKELL AVE 91406

Application / Permit
22016-10000-17038
Plan Check / Job No.
B22LA10860
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
CHANGE OF USE FROM WAREHOUSE AND GYM TO WAREHOUSE. TENAT IMPROVEMENT: NEW NON-BEARING METAL PARTITION WALLS, RELOCATE RESTROOMS, REVISE ELECTRICAL & PLUMBING, PROVIDE ACCESSIBLE PATH OF TRAVEL FROM PARKING TO BUILDING ENTRANCE.
Permit Issued
Issued on 9/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 ALBERT SERVIN
Corrections Issued 6/28/2022 ALBERT SERVIN
Quality Review Completed 6/29/2022 PETER KIM
Building Plans Picked Up 7/1/2022 APPLICANT
Disabled Access Plans Picked Up 7/8/2022 APPLICANT
Applicant returned to address corrections 7/14/2022 ALBERT SERVIN
Applicant returned to address corrections 7/15/2022 ALBERT SERVIN
Applicant returned to address corrections 7/19/2022 ALBERT SERVIN
Applicant returned to address corrections 7/29/2022 ALBERT SERVIN
Plan Check Approved 8/23/2022 ALBERT SERVIN
Issued 9/14/2022 APPLICANT
CofO in Progress 4/15/2024 DEANDRE HOFFMAN
Permit Finaled 4/17/2024 JEFFREY DURAN
CofO Issued 4/17/2024 JEFFREY DURAN
Permit Finaled 4/17/2024 JEFFREY DURAN

Permit Application Clearance Information

Sewer availability Cleared 7/27/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/28/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/28/2022 LEE GUILBEAUX
Public Works-Sewers Cleared 7/28/2022 LEE GUILBEAUX
DAS Clearance Cleared 8/18/2022 ALBERT SERVIN

Contact Information

Architect Estrada,, Felipe S; Lic. No.: C19010 18763 CENTER ST      ORANGE, CA 92869
Contractor Ramsay Construction Inc; Lic. No.: 985675-B 4228 LADOGA AVENUE      LAKEWOOD, CA 90716

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/12/2023 Not Ready for Inspection DEANDRE HOFFMAN
Pre-Inspection 1/25/2023 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 1/26/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 1/31/2023 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 2/6/2023 Partial Inspection JEFFREY FULTON
Partition/T-Bar Ceiling 4/5/2023 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 4/6/2023 Approved STEVEN LEVITT
Wood Frame 4/6/2023 Partial Inspection DEANDRE HOFFMAN
Partition/T-Bar Ceiling 4/11/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 4/14/2023 Partial Inspection DEANDRE HOFFMAN
Final 4/15/2023 Not Ready for Inspection DEANDRE HOFFMAN
Reinforced Masonry Frame 4/15/2023 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 4/15/2023 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 4/15/2023 Approved DEANDRE HOFFMAN
Special/Order Compliance 12/11/2023 Partial Inspection DEANDRE HOFFMAN
Final 4/10/2024 Partial Inspection DEANDRE HOFFMAN
Final 4/15/2024 OK to Issue CofO DEANDRE HOFFMAN