959 N SEWARD ST 90038

Certificate Information: 959 N SEWARD ST 90038

Application / Permit
22016-10000-16988
Plan Check / Job No.
B22LA10820
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan Renovation of exterior courtyard within an existing office development including landscape, hardscape, seating, canopy/trellis, retail kiosk, and fence with gate.
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
Permit Finaled on 1/2/2024

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Disabled Access Plans Picked Up 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 SERGIO GUTIERREZ
Corrections Issued 8/12/2022 SERGIO GUTIERREZ
Quality Review Completed 8/17/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/20/2022 SERGIO GUTIERREZ
Plan Check Approved 11/8/2022 SERGIO GUTIERREZ
Issued 4/25/2023 APPLICANT
Permit Finaled 12/29/2023 GREGORY POMISH

Permit Application Clearance Information

"Q" conditions Cleared 8/23/2022 RYAN LY
"T" removal Cleared 8/23/2022 RYAN LY
Miscellaneous Cleared 8/23/2022 RYAN LY
Miscellaneous Cleared 8/23/2022 RYAN LY
Miscellaneous Cleared 8/23/2022 RYAN LY
Low Impact Development Cleared 9/27/2022 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 9/27/2022 AMMAR ELTAWIL
DAS Clearance Cleared 9/28/2022 Hernan Arreola
Eng Process Fee Ord 176,300 Cleared 9/29/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 9/29/2022 JEANIE LAM
Green Code Cleared 10/25/2022 AARON COSTA

Contact Information

Architect Rios,, Mark William; Lic. No.: NA15744       ,
Contractor Tectonics Construction Inc; Lic. No.: 705550-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 5/17/2023 Partial Approval ALFREDO LOPEZ
SWPPP-Const. Storm Water 6/8/2023 Completed JEROME BLACKWOOD
Deputy Grading 6/22/2023 Partial Approval ALFREDO LOPEZ
Footing/Foundation/Slab 6/22/2023 Partial Approval ALFREDO LOPEZ
Footing/Foundation/Slab 6/28/2023 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 7/5/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/10/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/12/2023 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 7/13/2023 Approved JEROME BLACKWOOD
Footing/Foundation/Slab 7/13/2023 Partial Approval JEROME BLACKWOOD
Deputy Drilled-In Anchors 7/17/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Concrete 7/17/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/17/2023 Order to Comply Issued JEROME BLACKWOOD
Deputy Drilled-In Anchors 7/20/2023 No Access for Inspection JEROME BLACKWOOD
Deputy Reinf. Concrete 7/20/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/20/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/24/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 7/26/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 8/4/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 8/9/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 8/23/2023 Approved RONALD JIMENEZ
Drywall Nailing 8/25/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 8/25/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 8/28/2023 Not Ready for Inspection JEROME BLACKWOOD
Structural Steel Frame 10/10/2023 Partial Approval JEROME BLACKWOOD
Final 11/29/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 11/29/2023 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 11/29/2023 Approved ALFREDO LOPEZ
Final 12/29/2023 Permit Finaled GREGORY POMISH