959 N SEWARD ST 90038
Certificate Information: 959 N SEWARD ST 90038
- Application / Permit
- 22016-10000-16988
- Plan Check / Job No.
- B22LA10820
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan Renovation of exterior courtyard within an existing office development including landscape, hardscape, seating, canopy/trellis, retail kiosk, and fence with gate.
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/2/2024
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 8/12/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/17/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/20/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/8/2022 | SERGIO GUTIERREZ |
| Issued | 4/25/2023 | APPLICANT |
| Permit Finaled | 12/29/2023 | GREGORY POMISH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/23/2022 | RYAN LY |
| "T" removal | Cleared | 8/23/2022 | RYAN LY |
| Miscellaneous | Cleared | 8/23/2022 | RYAN LY |
| Miscellaneous | Cleared | 8/23/2022 | RYAN LY |
| Miscellaneous | Cleared | 8/23/2022 | RYAN LY |
| Low Impact Development | Cleared | 9/27/2022 | AMMAR ELTAWIL |
| Stormwater Pollution Mitigatn | Cleared | 9/27/2022 | AMMAR ELTAWIL |
| DAS Clearance | Cleared | 9/28/2022 | Hernan Arreola |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | JEANIE LAM |
| Green Code | Cleared | 10/25/2022 | AARON COSTA |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: NA15744 | , |
| Contractor | Tectonics Construction Inc; Lic. No.: 705550-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/17/2023 | Partial Approval | ALFREDO LOPEZ |
| SWPPP-Const. Storm Water | 6/8/2023 | Completed | JEROME BLACKWOOD |
| Deputy Grading | 6/22/2023 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 6/22/2023 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 6/28/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 7/5/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/12/2023 | Partial Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 7/13/2023 | Approved | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 7/17/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 7/17/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/17/2023 | Order to Comply Issued | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 7/20/2023 | No Access for Inspection | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 7/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/24/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/26/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 8/4/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 8/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/23/2023 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 8/25/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/25/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 8/28/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Structural Steel Frame | 10/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 11/29/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 11/29/2023 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 11/29/2023 | Approved | ALFREDO LOPEZ |
| Final | 12/29/2023 | Permit Finaled | GREGORY POMISH |