8409 W MELROSE AVE 90069

Certificate Information: 8409 W MELROSE AVE 90069

Application / Permit
22016-10000-16977
Plan Check / Job No.
B22LA10809
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
COMBINE TWO (E) RETAIL SPACES, TENANT IMPROVEMENT.
Permit Issued
Issued on 12/28/2022
Issuing Office
Current Status
Permit Finaled on 4/24/2023

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 JOE VO
Corrections Issued 6/19/2022 DANIEL YIP
Quality Review Completed 7/5/2022 MICHAEL PEREZ
Plan Check Approved 12/13/2022 JOE VO
Issued 12/28/2022 APPLICANT
Permit Finaled 4/18/2023 JEROME BLACKWOOD

Permit Application Clearance Information

Green Code Cleared 9/28/2022 DONALD CRICHLOW
DAS Clearance Cleared 12/4/2022 ELIZABETH TOMS

Contact Information

Architect Valerio,, Niccolo; Lic. No.: C24228 5858 WILSHIRE BLVD # 203      LOS ANGELES, CA 90036
Architect Valerio,, Niccolo; Lic. No.: NA24228       ,
Contractor Ferrante Koberling Construction Inc; Lic. No.: 988562-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2023 Partial Approval JEROME BLACKWOOD
Pre-Inspection 1/18/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 1/25/2023 Partial Approval JEROME BLACKWOOD
Insulation 2/13/2023 Partial Approval JEROME BLACKWOOD
Insulation 2/14/2023 Corrections Issued JEROME BLACKWOOD
Green Building Rough 2/17/2023 Partial Approval JEROME BLACKWOOD
METHANE-Rough 2/17/2023 Partial Approval JEROME BLACKWOOD
Wood Frame 2/17/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 2/21/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 2/28/2023 Partial Inspection ALFREDO LOPEZ
T-Bar Ceiling 3/10/2023 Approved ALFREDO LOPEZ
T-Bar Ceiling 3/13/2023 Not Ready for Inspection JEROME BLACKWOOD
Final 3/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 3/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 3/31/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Final 3/31/2023 Conditional Approval JEROME BLACKWOOD
METHANE-Rough 3/31/2023 Conditional Approval JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 3/31/2023 Approved JEROME BLACKWOOD
Wood Frame 3/31/2023 Conditional Approval JEROME BLACKWOOD
Final 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Final 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Rough 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Not Ready JEROME BLACKWOOD
Wood Frame 4/6/2023 Not Ready for Inspection JEROME BLACKWOOD
Special/Order Compliance 4/7/2023 Approved EDWIN GREGORYONA
Special/Order Compliance 4/7/2023 Partial Approval JEROME BLACKWOOD
Special/Order Compliance 4/11/2023 Conditional Approval JEROME BLACKWOOD
Final 4/18/2023 Permit Finaled JEROME BLACKWOOD
Green Building Final 4/18/2023 Approved JEROME BLACKWOOD
Green Building Rough 4/18/2023 Approved JEROME BLACKWOOD
METHANE-Final 4/18/2023 Approved JEROME BLACKWOOD
METHANE-Rough 4/18/2023 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Required JEROME BLACKWOOD
Wood Frame 4/18/2023 Approved JEROME BLACKWOOD