863 1/2 S NORTON AVE 90005
Certificate Information: 863 1/2 S NORTON AVE 90005
- Application / Permit
- 22016-10000-16928
- Plan Check / Job No.
- B22LA10772
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RECREATION ROOM (WHICH IS ATTACHED TO A GARAGE WITH STORAGE) INTO ADU, CREATING DETACHED ADU (497.7 SF) PER CA Govt. Code 65852.2(e)(1)(B) WITH ATTACHED STORAGE AND GARAGE
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | JOSEPH RAFOLS |
| Corrections Issued | 6/3/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 8/24/2022 | JOSEPH RAFOLS |
| Issued | 9/29/2022 | APPLICANT |
| CofO in Progress | 2/1/2023 | JEFFREY MEAD |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
| CofO Issued | 3/9/2023 | DEROLD HAUFF |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 7/12/2022 | AMANDA KAINER |
| Address approval | Cleared | 8/11/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/11/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/4/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Pre-Inspection | 10/4/2022 | Approved | JEFFREY MEAD |
| Sewer | 10/4/2022 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 10/4/2022 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 10/13/2022 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 10/21/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/21/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 10/21/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/28/2022 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 10/28/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 11/9/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 11/9/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/18/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/6/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/12/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 12/12/2022 | Approved | JEFFREY MEAD |
| Final | 1/24/2023 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 1/24/2023 | Approved | JEFFREY MEAD |
| Final | 1/27/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 2/1/2023 | Approved | JEFFREY MEAD |
| Final | 2/1/2023 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 2/1/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/1/2023 | Approved | JEFFREY MEAD |