4230 S TERRAZA DR 90008
Certificate Information: 4230 S TERRAZA DR 90008
- Application / Permit
- 22016-10000-16851
- Plan Check / Job No.
- B22LA10708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Interior remodel to relocate kitchen and dining room, add (1) bathroom within and remodel (3) existing bathrooms. Remove and replace all doors and windows. Replace (3) roof beams due to water damage. All work per structural engineering design
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/10/2024
Permit Application Status History
| Submitted | 6/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2022 | KHUONG TRUONG |
| Corrections Issued | 6/8/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/19/2022 | KHUONG TRUONG |
| Issued | 8/30/2022 | APPLICANT |
| Permit Finaled | 1/10/2024 | ANTHONY EGSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/19/2022 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/12/2022 | Partial Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Partial Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 9/12/2022 | Partial Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/19/2022 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 9/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 10/21/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/5/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 12/5/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 12/5/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/9/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/9/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 2/1/2023 | Approved | ANTHONY EGSON |
| Insulation | 2/9/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/9/2023 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 2/24/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/7/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 12/7/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/7/2023 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 12/7/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 12/7/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/8/2024 | Approved | ANTHONY EGSON |
| Final | 1/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 1/8/2024 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 1/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/10/2024 | Permit Finaled | ANTHONY EGSON |