2646 1/2 S DOLPHIN AVE 90731
Certificate Information: 2646 1/2 S DOLPHIN AVE 90731
- Application / Permit
- 22016-10000-16715
- Plan Check / Job No.
- B22LA10593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF PORTION OF GARAGE (182 SF) AND RECREATION ROOM (542 SF) TO ACCESSORY DWELLING UNIT, TOTAL ADU AREA WILL BE 724 SF PER STATE LAW
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO Issued on 1/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2022 | KHUONG TRUONG |
| Corrections Issued | 6/11/2022 | KHUONG TRUONG |
| Plan Check Approved | 11/13/2023 | KHUONG TRUONG |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 1/12/2026 | ANSON MAGLASANG |
| Permit Finaled | 1/12/2026 | ANSON MAGLASANG |
| CofO Issued | 1/12/2026 | ANSON MAGLASANG |
| Permit Finaled | 1/12/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2022 | ANA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2022 | ANA VILLA |
| Sewer availability | Cleared | 7/11/2022 | ANA VILLA |
| Coastal Zone | Cleared | 11/7/2023 | RUBEN VASQUEZ |
| Coastal Zone | Cleared | 11/7/2023 | RUBEN VASQUEZ |
Contact Information
| Contractor | Luxe Home Remodel Inc; Lic. No.: 1029483-B | , |
| Engineer | Banning,, George Kwame; Lic. No.: NA53074 | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/23/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/27/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/27/2025 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/19/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/19/2025 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/19/2025 | Conditional Approval | JOSEPH MCGARRY |
| HVAC-Rough | 2/19/2025 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/19/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/3/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 3/3/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 3/3/2025 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/3/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/10/2025 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/10/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 3/10/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/13/2025 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 3/14/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/28/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/28/2025 | Approved | JOSEPH MCGARRY |
| Final | 12/12/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 12/12/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 12/12/2025 | Approved | JOSEPH MCGARRY |
| Final | 1/8/2026 | OK to Issue CofO | JOSEPH MCGARRY |