6014 W SATURN ST 90035
Certificate Information: 6014 W SATURN ST 90035
- Application / Permit
- 22016-10000-16708
- Plan Check / Job No.
- B22LA10588
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Current Status
- CofO Issued on 11/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | DANIEL YIP |
| Corrections Issued | 6/10/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/6/2022 | DANIEL YIP |
| Plan Check Approved | 8/10/2022 | DANIEL YIP |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 6/3/2024 | ARTHUR NEGRETE |
| Permit Finaled | 11/11/2024 | DEROLD HAUFF |
| Permit Finaled | 11/11/2024 | DEROLD HAUFF |
| CofO Issued | 11/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/13/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | CELINA MORENO |
| Sewer availability | Cleared | 6/16/2022 | CELINA MORENO |
| Construction near power lines | Cleared | 8/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Oyz Developments Llc; Lic. No.: 1079567-B | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 8/23/2023 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 8/23/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 8/23/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/23/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 9/20/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 10/19/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | JOSH MEISTER |
| PLUMBING-Rough | 11/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Wood Frame | 11/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/20/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 11/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/8/2023 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 12/18/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/18/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/27/2023 | Conditional Approval | LILIANA PORTILLO |
| Wood Frame | 12/27/2023 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 1/3/2024 | Approved | RONNIE MINDANAO |
| Insulation | 1/3/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/3/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 1/24/2024 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/19/2024 | Corrections Issued | RICHARD DOCKUS |
| Final | 4/19/2024 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 4/19/2024 | Approved | RICHARD DOCKUS |
| HVAC-Final | 4/19/2024 | Corrections Issued | RICHARD DOCKUS |
| METHANE-Final | 4/19/2024 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 4/19/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 4/19/2024 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 4/19/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/7/2024 | Approved | RICHARD DOCKUS |
| Final | 5/7/2024 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 5/7/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 5/7/2024 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Approved | RICHARD DOCKUS |
| Final | 5/28/2024 | Partial Approval | ARTHUR NEGRETE |
| Final | 5/31/2024 | OK to Issue CofO | ARTHUR NEGRETE |