10700 W HOLMAN AVE 90024

Certificate Information: 10700 W HOLMAN AVE 90024

Application / Permit
22016-10000-16605
Plan Check / Job No.
B22LA10492
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPlan: Soft-Story seismic retrofit per LABC Chapter 93: Eliminate the soft story condition that exist along the east side of the building by installing Special Steel cantilever column at open wall along the east end of building.
Permit Issued
Issued on 10/26/2022
Issuing Office
Current Status
CofC Issued on 2/23/2023

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 JESSE VIDUYA
Corrections Issued 6/14/2022 JESSE VIDUYA
Quality Review Completed 6/22/2022 HANS SANTIAGO
Applicant returned to address corrections 8/11/2022 JESSE VIDUYA
Plan Check Approved 8/19/2022 JESSE VIDUYA
Issued 10/26/2022 APPLICANT
OK for CofC 2/3/2023 PAUL DAVIDSON
CofC Issued 2/23/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/24/2022 RICARDO BOHORQUEZ

Contact Information

Contractor H Z S Construction; Lic. No.: 1039476-B 1720 E GARRY AVE #229      SANTA ANA, CA 92705
Engineer Shekaramiz,, Hamid; Lic. No.: C82784 2 TIMBRE      RANCHO SANTA MARGARITA, CA 92688

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2022 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 12/16/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 12/20/2022 Conditional Approval GRANT WOODS
Wood Frame 12/21/2022 Approved GRANT WOODS
Interior/Exterior Lathing 12/28/2022 Approved AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Not Ready SHAVONNE ESPINOZA
Final 2/3/2023 OK for CofC PAUL DAVIDSON
METHANE-Final 2/3/2023 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 2/3/2023 Approved PAUL DAVIDSON