19114 W CALVERT ST 91335
Certificate Information: 19114 W CALVERT ST 91335
- Application / Permit
- 22016-10000-16529
- Plan Check / Job No.
- B22LA10427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage and workroom to ADU per state law. Create exterior powder room.
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | RICARDO RAMIREZ |
| Corrections Issued | 5/31/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 6/13/2022 | JAD BASMA |
| Issued | 6/13/2022 | APPLICANT |
| CofO in Progress | 11/15/2022 | SEAN HAUPT |
| Permit Finaled | 4/24/2023 | MICHAEL SMITH |
| CofO Issued | 4/24/2023 | MICHAEL SMITH |
| Permit Finaled | 4/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/4/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/22/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 6/22/2022 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 6/29/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/1/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 7/15/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 7/15/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 7/15/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 7/15/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 7/27/2022 | Approved | MORRIS JACKSON |
| Gas Test | 8/8/2022 | Approved | MORRIS JACKSON |
| Final | 9/6/2022 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 9/6/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 9/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 9/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 9/27/2022 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 9/27/2022 | Approved | SEAN HAUPT |
| Final | 10/17/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 11/14/2022 | OK to Issue CofO | SEAN HAUPT |