1152 S LUCERNE BLVD 90019

Certificate Information: 1152 S LUCERNE BLVD 90019

Application / Permit
22016-10000-16394
Plan Check / Job No.
B22LA10322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING DETACHED 2ND FLOOR RECREATION ROOM TO ACCESSORY DWELLING UNIT (431sf) PER CA GOV'T CODE 65852.2(e)(1)(A). 1st FLOOR 2-CAR GARAGE TO REMAIN.
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 HANS SANTIAGO
Corrections Issued 6/4/2022 HANS SANTIAGO
Plan Check Approved 6/25/2022 ANDREW SANTIAGO
Issued 8/19/2022 APPLICANT
CofO in Progress 2/16/2024 JUSTIN HAWLEY
CofO Issued 2/28/2024 DEROLD HAUFF
Permit Finaled 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/21/2022 AMAAN MALIK
Sewer availability Cleared 6/21/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/24/2022 AMAAN MALIK

Contact Information

Contractor Migsta Construction Inc; Lic. No.: 1035306-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/30/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 8/30/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/23/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 9/23/2022 Approved SCOTT FINNILA
FLOOD-Proofing Certificate 9/23/2022 Partial Inspection SCOTT FINNILA
HVAC-Rough 9/23/2022 Corrections Issued SCOTT FINNILA
Insulation 9/23/2022 Partial Approval SCOTT FINNILA
METHANE-Rough 9/23/2022 Partial Inspection SCOTT FINNILA
Drywall Nailing 10/20/2022 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 10/20/2022 Not Ready for Inspection STUART CHAPMAN
Insulation 11/7/2022 Approved STUART CHAPMAN
Drywall Nailing 11/10/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/16/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 12/16/2022 Not Ready for Inspection CALEB MEISTER
FLOOD-Proofing Certificate 12/16/2022 Not Ready for Inspection CALEB MEISTER
Final 12/16/2022 Corrections Issued CALEB MEISTER
HVAC-Final 12/16/2022 Not Ready for Inspection CALEB MEISTER
METHANE-Final 12/16/2022 Not Ready for Inspection CALEB MEISTER
METHANE-Rough 12/16/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Final 12/16/2022 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 12/16/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 1/10/2023 Conditional Approval CALEB MEISTER
FLOOD-Proofing Certificate 1/10/2023 Not Ready for Inspection CALEB MEISTER
Final 1/10/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Final 1/10/2023 Approved CALEB MEISTER
METHANE-Rough 1/10/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Approved CALEB MEISTER
BUILDING-Rough-Frame 2/16/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 2/16/2024 Approved JUSTIN HAWLEY
Final 2/16/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 2/16/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 2/16/2024 Approved JUSTIN HAWLEY