1152 S LUCERNE BLVD 90019
Certificate Information: 1152 S LUCERNE BLVD 90019
- Application / Permit
- 22016-10000-16394
- Plan Check / Job No.
- B22LA10322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING DETACHED 2ND FLOOR RECREATION ROOM TO ACCESSORY DWELLING UNIT (431sf) PER CA GOV'T CODE 65852.2(e)(1)(A). 1st FLOOR 2-CAR GARAGE TO REMAIN.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | HANS SANTIAGO |
| Corrections Issued | 6/4/2022 | HANS SANTIAGO |
| Plan Check Approved | 6/25/2022 | ANDREW SANTIAGO |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 2/16/2024 | JUSTIN HAWLEY |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/21/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2022 | AMAAN MALIK |
Contact Information
| Contractor | Migsta Construction Inc; Lic. No.: 1035306-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/30/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 8/30/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/23/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/23/2022 | Approved | SCOTT FINNILA |
| FLOOD-Proofing Certificate | 9/23/2022 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 9/23/2022 | Corrections Issued | SCOTT FINNILA |
| Insulation | 9/23/2022 | Partial Approval | SCOTT FINNILA |
| METHANE-Rough | 9/23/2022 | Partial Inspection | SCOTT FINNILA |
| Drywall Nailing | 10/20/2022 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 11/7/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/10/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| FLOOD-Proofing Certificate | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| Final | 12/16/2022 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Final | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Rough | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 12/16/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 1/10/2023 | Conditional Approval | CALEB MEISTER |
| FLOOD-Proofing Certificate | 1/10/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 1/10/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Final | 1/10/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 1/10/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/16/2024 | Approved | JUSTIN HAWLEY |
| Final | 2/16/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 2/16/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/16/2024 | Approved | JUSTIN HAWLEY |