5436-5438 N TYRONE AVE 91401

Certificate Information: 5436-5438 N TYRONE AVE 91401

Application / Permit
22016-10000-16188
Plan Check / Job No.
B22LA10166
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
eplan Convert Existing attached garage to JADU 367 sft per CA Govt. Code 65852.2(e)(1)(A) and 65852.229.
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 4/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/6/2022 LUKE GONZALES
Corrections Issued 6/7/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 6/29/2022 LUKE GONZALES
Plan Check Approved 7/7/2022 LUKE GONZALES
Issued 7/11/2022 APPLICANT
CofO in Progress 3/14/2024 RYAN SALAZAR
Permit Finaled 4/24/2024 RUBEN SALAS
CofO Issued 4/24/2024 RUBEN SALAS
Permit Finaled 4/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/21/2022 CARLOS AGUILERA
Sewer availability Cleared 6/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/27/2022 CARLOS AGUILERA

Contact Information

Contractor Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2022 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 9/27/2022 Corrections Issued DEANDRE HOFFMAN
Footing/Foundation/Slab 10/6/2022 Approved RICHARD DOCKUS
Wood Frame 10/6/2022 Partial Approval RICHARD DOCKUS
Green Building Rough 10/18/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 10/18/2022 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 10/18/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 10/21/2022 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Approval CALEB MEISTER
Green Building Rough 11/16/2022 Approved RICHARD DOCKUS
Wood Frame 11/16/2022 Corrections Issued RICHARD DOCKUS
Wood Frame 1/27/2023 Partial Approval RYAN SALAZAR
Insulation 2/3/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/3/2023 Approved RYAN SALAZAR
Drywall Nailing 2/10/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Not Ready RYAN SALAZAR
Final 10/10/2023 Corrections Issued RYAN SALAZAR
Green Building Final 10/10/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/10/2023 Approved RYAN SALAZAR
Wood Frame 10/10/2023 Approved RYAN SALAZAR
Final 3/13/2024 OK to Issue CofO RYAN SALAZAR
Special/Order Compliance 3/26/2024 Corrections Issued RYAN SALAZAR