3928 S INGLEWOOD BLVD 90066
Certificate Information: 3928 S INGLEWOOD BLVD 90066
- Application / Permit
- 22016-10000-16164
- Plan Check / Job No.
- B22LA10150
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan CONVERT (E) ATTACHED CARPOT TO ADU PER GCS 65852.2(e)(1)(C) FOR EXISTING MULTI-FAMILY
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Current Status
- CofO Issued on 2/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | ADRIANA LOPEZ |
| Corrections Issued | 7/13/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 7/18/2022 | GARO TELMI |
| Plan Check Approved | 11/7/2022 | ADRIANA LOPEZ |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 2/12/2024 | FARHAD DADBIN |
| Permit Finaled | 2/13/2024 | DAVID TSAU |
| CofO Issued | 2/13/2024 | DAVID TSAU |
| Permit Finaled | 2/13/2024 | DAVID TSAU |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/12/2022 | JENSON LEE |
| Tenant Habitability Plan | Cleared | 8/17/2022 | MICHAEL SOTO |
| Miscellaneous | Cleared | 9/9/2022 | ANDREW SANTIAGO |
| Address approval | Cleared | 10/5/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2022 | JENSON LEE |
Contact Information
| Architect | Wang,, Yang; Lic. No.: C35954 | 216 W. GARVEY AVENUE_UNIT D MONTEREY PARK, CA 91754 |
| Contractor | G B Developing Corp; Lic. No.: 929207-B | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 9/22/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 10/18/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 10/20/2023 | Corrections Issued | FARHAD DADBIN |
| Insulation | 10/23/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 10/23/2023 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 10/31/2023 | Approved | FARHAD DADBIN |
| Final | 1/4/2024 | Conditional Approval | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 1/4/2024 | Approved | FARHAD DADBIN |
| Wood Frame | 1/4/2024 | Approved | FARHAD DADBIN |
| Final | 2/12/2024 | OK to Issue CofO | FARHAD DADBIN |