610 N FORMOSA AVE 90036
Certificate Information: 610 N FORMOSA AVE 90036
- Application / Permit
- 22016-10000-16161
- Plan Check / Job No.
- B22LA10149
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: INGRESS AND EGRESS ADDIITON TO AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Current Status
- CofO Issued on 11/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | DANIEL YIP |
| Corrections Issued | 8/1/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/10/2022 | DANIEL YIP |
| Plan Check Approved | 10/20/2022 | DANIEL YIP |
| Issued | 10/20/2022 | APPLICANT |
| CofO in Progress | 10/13/2023 | LILIANA PORTILLO |
| Permit Finaled | 11/1/2023 | DEROLD HAUFF |
| CofO Issued | 11/1/2023 | DEROLD HAUFF |
| Permit Finaled | 11/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | CELINA MORENO |
| Sewer availability | Cleared | 9/15/2022 | CELINA MORENO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/23/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 1/26/2023 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 1/26/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 1/26/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/5/2023 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/6/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 4/6/2023 | Approved | MICHAEL LEWIS |
| Insulation | 4/10/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/13/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/4/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/4/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/26/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/6/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 10/6/2023 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 10/6/2023 | Approved | LILIANA PORTILLO |
| Green Building Final | 10/6/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/6/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/6/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 10/6/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/12/2023 | Approved | LILIANA PORTILLO |
| Final | 10/12/2023 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 10/12/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/12/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | LILIANA PORTILLO |