518 N GRAMERCY PL 1-61 90004
Certificate Information: 518 N GRAMERCY PL 1-61 90004
- Application / Permit
- 22016-10000-16126
- Plan Check / Job No.
- B22LA10120
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 3,575 SF OF (E) 20,300 SF TYPE 1-A FIRST FLOOR GARAGE OF AN (E) 51 APARTMENT INTO 10 ADU'S.
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 6/17/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/24/2022 | KEN GILL |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 7/12/2022 | APPLICANT |
| Plan Check Approved | 4/25/2023 | ARSALAN SHABESTARI |
| Issued | 5/8/2023 | APPLICANT |
| Green Plans Picked Up | 6/9/2023 | APPLICANT |
| Permit Finaled | 6/9/2026 | ADAM BURGESS |
| CofO Issued | 6/9/2026 | ADAM BURGESS |
| Permit Finaled | 6/9/2026 | ADAM BURGESS |
Permit Application Clearance Information
| Green Code | Cleared | 11/15/2022 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| Address approval | Cleared | 1/6/2023 | CELINA MORENO |
| Sewer availability | Cleared | 1/6/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | CELINA MORENO |
| DAS Clearance | Cleared | 2/3/2023 | ARSALAN SHABESTARI |
| Fire Marshal Fire Life Safety | Cleared | 4/20/2023 | ANDREW KO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2023 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 10/26/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Masonry Wall/Backfill | 12/8/2023 | Partial Inspection | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/21/2023 | Partial Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 12/21/2023 | Partial Inspection | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/27/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 1/17/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/17/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/8/2024 | Partial Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/21/2024 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 3/26/2024 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 3/28/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/26/2024 | Partial Approval | TIMOTHY POWELL |
| Insulation | 5/9/2024 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 5/22/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 6/4/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 11/8/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 2/11/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 2/19/2025 | Approved | TIMOTHY POWELL |
| Green Building Final | 3/11/2026 | Approved | RONALD JIMENEZ |
| Green Building Rough | 3/11/2026 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 3/11/2026 | Approved | RONALD JIMENEZ |
| Reinforced Concrete Frame | 3/11/2026 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 3/11/2026 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 3/31/2026 | Partial Approval | LUIS CCAMACHO |
| Smoke Detectors | 3/31/2026 | Approved | LUIS CCAMACHO |