5454 S BEETHOVEN ST 90066

Certificate Information: 5454 S BEETHOVEN ST 90066

Application / Permit
22016-10000-16123
Plan Check / Job No.
B22LA10118
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan ePlan Tenant Improvement of existing office building
Permit Issued
Issued on 11/4/2022
Issuing Office
Current Status
Permit Finaled on 12/13/2023

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 FARSHAD ALIMOHAMADI
Corrections Issued 6/21/2022 FARSHAD ALIMOHAMADI
Quality Review Completed 6/21/2022 CHARLES CHANG
Applicant returned to address corrections 8/9/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/12/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 11/2/2022 FARSHAD ALIMOHAMADI
Issued 11/4/2022 APPLICANT
Permit Finaled 12/13/2023 MICHAEL PETRUSKO

Permit Application Clearance Information

Green Code Cleared 8/19/2022 FARSHAD ALIMOHAMADI
Fire Marshal Fire Life Safety Cleared 10/5/2022 DOMINIQUE MEDINA
DAS Clearance Cleared 10/20/2022 ELIZABETH TOMS

Contact Information

Architect Govin,, Daniel Casey; Lic. No.: C39512 1928 NW 18TH ST      OKLAHOMA CITY, OK 73106
Contractor Corporate Contractors Inc; Lic. No.: 604407-B 2550 CORPORATE PL STE C-111      MONTEREY PARK, CA 91754

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/9/2022 Approved GRANT WOODS
Light Gage Steel Frame 11/9/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 11/14/2022 Conditional Approval GRANT WOODS
Structural Steel Frame 11/14/2022 Partial Inspection GRANT WOODS
Wall Anchors 11/14/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 11/17/2022 Conditional Approval GRANT WOODS
Drywall Nailing 11/28/2022 Approved ALAN NOVAK
Deputy Drilled-In Anchors 11/29/2022 Approved GRANT WOODS
Deputy Steel/Welding 11/29/2022 Approved GRANT WOODS
Light Gage Steel Frame 11/29/2022 Partial Inspection GRANT WOODS
Deputy Drilled-In Anchors 11/30/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 11/30/2022 Conditional Approval GRANT WOODS
Light Gage Steel Frame 12/9/2022 Partial Approval GRANT WOODS
Drywall Nailing 12/28/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 1/10/2023 Partial Approval GRANT WOODS
T-Bar Ceiling 1/10/2023 Partial Approval GRANT WOODS
T-Bar Ceiling 1/12/2023 Partial Approval GRANT WOODS
Drywall Nailing 1/18/2023 Approved MICHAEL PETRUSKO
Drywall Nailing 1/24/2023 Not Ready for Inspection GRANT WOODS
Drywall Nailing 1/25/2023 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 2/7/2023 Approved AMANUEL BERHE
T-Bar Ceiling 2/16/2023 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Not Ready GRANT WOODS
Final 12/5/2023 Not Ready for Inspection DAVID TSAU
Green Building Final 12/5/2023 Approved DAVID TSAU
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved DAVID TSAU
Smoke Detectors 12/5/2023 Approved DAVID TSAU
Final 12/13/2023 Permit Finaled MICHAEL PETRUSKO