2621 1/2 W SCOTT AVE 90026
Certificate Information: 2621 1/2 W SCOTT AVE 90026
- Application / Permit
- 22016-10000-15896
- Plan Check / Job No.
- B22LA09916
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert porition of the second story of (E) two-story Single Family Dwelling to a Junior Accessory Dwelling Unit (480 sq ft) per GCS 65852.2(e)(1)(C)(E). COMPLY WITH DEPARTMENT ORDER effective date 09/03/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Metro
- Current Status
- Issued on 7/28/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | FERNANDO FLORES |
| Corrections Issued | 5/25/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Applicant returned to address corrections | 6/27/2022 | FERNANDO FLORES |
| Plan Check Approved | 7/14/2022 | FERNANDO FLORES |
| Issued | 7/28/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2022 | CINDY QI |
| Sewer availability | Cleared | 6/3/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | CINDY QI |
Contact Information
| Architect | Ragle,, Benjamin David; Lic. No.: C32039 | 1608 MORTON AVENUE LOS ANGELES, CA 90026 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2023 | Approved | PTOLEMY HILL |
| Footing/Foundation/Slab | 4/3/2024 | Approved | COREY HUPP |
| Drywall Nailing | 4/16/2024 | Partial Approval | COREY HUPP |
| Wood Frame | 4/16/2024 | Partial Approval | COREY HUPP |
| Wood Frame | 4/22/2024 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 4/23/2024 | Partial Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/14/2024 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | COREY HUPP |
| HVAC-Rough | 9/26/2024 | Approved | COREY HUPP |
| Drywall Nailing | 10/1/2024 | Approved | ROBERT NILES |
| Final | 5/21/2025 | Corrections Issued | ROBERT NILES |
| Final | 6/11/2025 | Conditional Approval | ROBERT NILES |