4329 S STEWART AVE 90066
Certificate Information: 4329 S STEWART AVE 90066
- Application / Permit
- 22016-10000-15881
- Plan Check / Job No.
- B22LA09897
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Conversion of (E) Detached Garage (372 SF) into ADU (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | AUNG SOE |
| Corrections Issued | 5/31/2022 | AUNG SOE |
| Applicant returned to address corrections | 6/11/2022 | AUNG SOE |
| Plan Check Approved | 6/25/2022 | AUNG SOE |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 2/7/2023 | HERBERT GIRON |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
| CofO Issued | 2/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 6/7/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 6/8/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | DINAH GARIN |
Contact Information
| Contractor | Udi'S Construction Inc; Lic. No.: 1056277-B | 5940 LAS VERGINES RD #659 CALABASAS, CA 91302 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2022 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/9/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/16/2022 | Approved | HERBERT GIRON |
| Sewer | 9/16/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 9/19/2022 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 11/4/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 11/4/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 11/4/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 11/7/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/7/2022 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 11/7/2022 | Not Ready for Inspection | HERBERT GIRON |
| Sewer | 11/7/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 11/15/2022 | Approved | HERBERT GIRON |
| Insulation | 11/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 11/15/2022 | Conditional Approval | HERBERT GIRON |
| Deputy Wood Construction | 11/16/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/18/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 11/18/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | HERBERT GIRON |
| Insulation | 11/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 11/23/2022 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 11/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Approved | HERBERT GIRON |
| Insulation | 12/2/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/2/2022 | Partial Approval | HERBERT GIRON |
| Shower Pan | 12/2/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/13/2022 | Approved | EVAN COOPER |
| Gas Test | 12/13/2022 | Corrections Issued | EVAN COOPER |
| Gas Test | 12/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 1/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 1/13/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 1/13/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 1/26/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/26/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/3/2023 | Corrections Issued | HERBERT GIRON |
| Final | 2/3/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 2/3/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 2/3/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 2/6/2023 | Approved | HERBERT GIRON |
| Final | 2/6/2023 | OK to Issue CofO | HERBERT GIRON |
| PLUMBING-Final | 2/6/2023 | Approved | HERBERT GIRON |