150 S SOTO ST 90033
Certificate Information: 150 S SOTO ST 90033
- Application / Permit
- 22016-10000-15818
- Plan Check / Job No.
- B22LA09846
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft story retrofit using 1 Special Steel Cantilever Column
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofC Issued on 12/9/2022
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | HANS SANTIAGO |
| Corrections Issued | 6/6/2022 | HANS SANTIAGO |
| Quality Review Completed | 6/7/2022 | SAI KHUM |
| Applicant returned to address corrections | 6/15/2022 | HANS SANTIAGO |
| Plan Check Approved | 6/27/2022 | ANDREW SANTIAGO |
| Issued | 7/22/2022 | APPLICANT |
| OK for CofC | 12/8/2022 | DARRYL ARNOLD |
| CofC Issued | 12/9/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/11/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | , |
| Contractor | U S Home Pros Inc; Lic. No.: 1022167-B | , |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2022 | Corrections Issued | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 8/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/7/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 9/7/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 9/7/2022 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 9/12/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/12/2022 | Approved | MARK FERRARI |
| Final | 12/6/2022 | Corrections Issued | VAHE KELEDJIAN |
| METHANE-Final | 12/6/2022 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 12/6/2022 | Approved | VAHE KELEDJIAN |
| Final | 12/8/2022 | OK for CofC | DARRYL ARNOLD |