7441 N JORDAN AVE 91303
Certificate Information: 7441 N JORDAN AVE 91303
- Application / Permit
- 22016-10000-15754
- Plan Check / Job No.
- B22LA09819
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 6/21/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/29/2022 | KEN GILL |
| Building Plans Picked Up | 7/5/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | ARSALAN SHABESTARI |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | ALEXANDER HANDY |
| No Progress | 1/27/2023 | JOHN JANSON |
| CofO in Progress | 2/21/2023 | ALEXANDER HANDY |
| CofO Issued-Status Void | 2/21/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 2/21/2023 | JOHN JANSON |
| Re-Activate Permit | 2/23/2023 | JOHN JANSON |
| Permit Finaled | 3/21/2023 | JOHN JANSON |
| CofO Corrected | 3/21/2023 | JOHN JANSON |
| Permit Finaled | 3/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/12/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/13/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/7/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2022 | Partial Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 11/2/2022 | Conditional Approval | STEVEN BACK |
| ELECTRICAL-Rough | 11/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 11/15/2022 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 11/22/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 11/22/2022 | Approved | STEVEN BACK |
| Special/Order Compliance | 11/22/2022 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 11/22/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/23/2022 | Partial Approval | STEVEN BACK |
| Sewer | 11/23/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 12/2/2022 | Approved | STEVEN BACK |
| Gas Test | 12/2/2022 | Partial Approval | STEVEN BACK |
| Insulation | 12/2/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/7/2022 | Approved | ALEXANDER HANDY |
| Final | 1/10/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/10/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/12/2023 | Approved | ALEXANDER HANDY |
| Final | 1/12/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 1/12/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/12/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 1/12/2023 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/12/2023 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 1/30/2023 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 2/24/2023 | Corrections Issued | ALEXANDER HANDY |