- ePlan Tenant improvement single-story retail building with exterior alteration and remove replace exisitng exterior windows and doors with structural upgrades.
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/11/2023
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/21/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 6/21/2022 | CHARLES CHANG |
| Applicant returned to address corrections | 7/27/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/12/2022 | FARSHAD ALIMOHAMADI |
| Issued | 9/14/2022 | APPLICANT |
| Permit Finaled | 7/11/2023 | RAFAEL CORTES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/4/2022 | Hernan Arreola |
| Green Code | Cleared | 8/4/2022 | AARON COSTA |
Contact Information
| Architect | Egan,, John S; Lic. No.: NA28572 | , |
| Contractor | Lucy Development Company; Lic. No.: 913288-B | , |
| Engineer | Wirthlin,, Jonathan Daniel; Lic. No.: NA5702 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2022 | Approved | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 11/22/2022 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 1/3/2023 | Partial Approval | ALAN MORELOS |
| Deputy Drilled-In Anchors | 1/24/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 1/24/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 2/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Wood Frame | 2/16/2023 | Partial Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 2/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 2/27/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 3/2/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Reinf. Concrete | 3/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Wood Construction | 3/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 3/29/2023 | Approved | ALAN MORELOS |
| Structural Steel Frame | 3/29/2023 | Partial Inspection | ALAN MORELOS |
| Wood Frame | 3/29/2023 | Approved | ALAN MORELOS |
| Insulation | 3/31/2023 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 4/4/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 4/5/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Approved | MARTIN TAVITIAN |
| Insulation | 4/5/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Approved | KATY RAMIREZ |
| Drywall Nailing | 4/26/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 4/26/2023 | Partial Approval | JAMES POWERS |
| Final | 6/29/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 6/29/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV No Gas | RAMAZANALI ALMASI |
| Smoke Detectors | 6/29/2023 | Approved | RAMAZANALI ALMASI |
| Final | 7/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/3/2023 | Approved | RAFAEL CORTES |
| Final | 7/11/2023 | Permit Finaled | RAFAEL CORTES |