534 S BERNAL AVE 90063
Certificate Information: 534 S BERNAL AVE 90063
- Application / Permit
- 22016-10000-15552
- Plan Check / Job No.
- B22LA09677
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing storage to an Accessory Dwelling Unit
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2022 | JOSEPH RAFOLS |
| Corrections Issued | 5/25/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 6/11/2022 | ZAW HAN |
| Plan Check Approved | 6/13/2022 | ZAW HAN |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 6/4/2025 | FREDDIE RIVERA |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
| CofO Issued | 6/5/2025 | DEROLD HAUFF |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/1/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/8/2022 | Approved | FREDDIE RIVERA |
| Sewer | 8/8/2022 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 8/8/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/5/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 11/22/2022 | Approved | CALEB MEISTER |
| Shower Pan | 11/22/2022 | Approved | CALEB MEISTER |
| Shower Pan | 12/8/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | FREDDIE RIVERA |
| Final | 2/15/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 2/15/2023 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 2/15/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 2/15/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 2/15/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 2/15/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 4/5/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 4/5/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/5/2023 | Approved | FREDDIE RIVERA |
| Final | 6/2/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 6/2/2025 | No Access for Inspection | FREDDIE RIVERA |
| Final | 6/4/2025 | OK to Issue CofO | FREDDIE RIVERA |